Installation
Avtron Outdoor Load Bank • Part Number K875A 1035409
3-1
SECTION III
INSTALLATION
INSTALLATION CHECKOUT PROCEDURE -
TO BE DONE PRIOR TO OPERATION
This Installation Checkout Procedure is intended to be used upon initial receipt of equipment and
following any relocation of a permanently mounted Load Bank. These procedures apply to Load
Banks in general and may include steps not relevant to the specific unit being installed. Disregard
those procedures which do not apply.
*************************************************************
W A R N I N G
THE FOLLOWING TESTS ARE TO BE ACCOMPLISHED BY A
QUALIFIED ELECTRICIAN OR TECHNICIAN USING
EXTREME CAUTION AS POTENTIALLY LETHAL VOLTAGES
AND DANGEROUS ROTATING COMPONENTS ARE PRESENT.
IF ASSISTANCE IS REQUIRED, AVTRON CAN PROVIDE
START UP SERVICE AT A NOMINAL CHARGE. AVTRON
ALSO WILL PROVIDE TELEPHONE ASSISTANCE IF
REQUIRED BY CALLING (216) 573-7600.
*************************************************************
1.
Verify the Load Bank placement meets the installation requirements found in the
INSTALLATION section of the instruction manual:
A.
Check the clearance from both intake and exhaust to any obstruction.
B.
If the location has a prevailing wind, make the wind aid in the cooling of the resistor
elements.
Summary of Contents for 1035409
Page 1: ...K875A 1035409...
Page 3: ......
Page 4: ......
Page 5: ......
Page 7: ......
Page 9: ......
Page 17: ......
Page 21: ......
Page 25: ......
Page 39: ......
Page 41: ......
Page 45: ......
Page 71: ......
Page 72: ......
Page 73: ......
Page 74: ......
Page 75: ......
Page 76: ......
Page 77: ......