Preparing for Commissioning
Installation & Commissioning Handbook, User Guide, AutroSafe Interactive Fire Alarm System, P-BSL330/IE,
Autronica Fire and Security AS
Page 10
3. Preparing for Commissioning
3.1 Introduction
The necessary preparations, include the following:
•
The dip-switches must be verified (factory set)
•
The BSL-330 module must be connected to a 24V DC power
source
•
The BSL-330 module must be connected to a computer's serial
port
•
The BSL-330 module must be set to Executive Mode
•
The required parameters must be set
3.2 Dip-switch Settings
The illustration below shows the dip-switch settings on the BSL-330
module.
Switch 1 = ON for RS-485 / 2-wire
Switch 1 = OFF for RS-422 / 4-wire
Switch 2 = OFF
Switch 3 = OFF
Switch 4 is not used.
The rotary switch on the front panel must be set to 0.
Normally, the necessary preparations for commissioning are
done by Autronica Fire and Security. These preparations are
described in this section.
4
ON
3
2
1
(front side)
(rear side)
Top View of BS-330 Module
4
ON
3
2
1
(front side)
(rear side)