INSTRUCTION MANUAL COMMERCIAL 2 CHARGING STATION
12
INSTALLATION RECOMMENDATIONS
The complex is installed on a 500x500x500 mm concrete base. We recommend to prepare
a special foundation with an installed metal plate (plates are available). The plate sizes of a
station stand for self-making the plate are given in the figure below.
ATTENTION!!!
Along with the preparation of the foundation, it is necessary to ensure the laying of the
power cable (not included in the delivery). Appropriate insulation must be used when
routing the power cable.
We recommend routing and connecting the power cable inside the charging system stand
before installing it on a concrete base.
The power cable must only be connected to the AC mains by qualified personnel.
Ensure before connecting the charger station that:
• The power cable (input) on the mains side is de-energised by external disconnecting
devices. We recommend installing a suitable 3-pole circuit breaker for a current of 80
A. The minimum cross-section of each lead wire should be at least 16 mm², the lead
material should be copper, twisted (5-16 mm²). For configuration: 1 connector Type 1 + 2
connectors Type 2, the cross section of the supply cable shall not be less than 35 mm² for
each core (circuit breaker for a current of 100 A, cable 5x35 mm²).
• The 380 V mains supply input has a 3-phase connection diagram with separate
conductors (L1, L2, L3 - phase; N - neutral; PE - «ground»).
Next, connect the input power cable to the AC mains to the corresponding input terminals
(L1 - color, L2 - color, L3 - color, N - blue, PE - yellow-green).
It is strictly forbidden to supply voltage to the mains input of the charging station when
grounding is not connected.
The base is cast in concrete. The ground at the
station location must ensure high stability of the
foundation. No underground cables or pipes shall
be laid in the foundation area.
The foundation usually takes about a week to
mature. Once the concrete has settled, you can
start the installation.
.