34

34

4

CHARGING SYSTEM TEST

The charging system consists of 1. the battery or battery bank, 2. the 

cables from the battery to the alternator and 3. the alternator. The 

proper sequence for testing the charging system is to begin with the 

battery or battery bank and then once the battery or battery bank is 

confirmed to be good and charged then the cables should be tested and 

finally after the cables have been confirmed to be good the alternator 

should be tested. If this sequence is not followed or if the alternator is 

tested with batteries that are low or bad or if the cables are weak the 

alternator could be misdiagnosed.

The previous sections explain the battery and battery bank tests and 

the next couple of sections explain the charging cable test and the 

alternator test.
.

 

--MAIN MENU--

 BATTERY BANK TEST

 VDROP MENU

 ALTERNATOR TEST

 STARTER DRAW TEST

 REVIEW/PRINT

 MULTIMETERS 

>J1708 DATA

--J1708 DATA--

>ATTACH J1708 DATA  
 CABLE.

'N' TO CANCEL

--J1708 DATA--

>TURN IGNITION KEY
 TO RUN.

'N' TO CANCEL

Attach the Optional J1708 Data Cable. 

If the cable is not correctly attached 

the test will not continue. Check 

the connection at the tester and the 

vehicle.

--J1708 DATA--

VIN: 123456789A
BATTERY 12.65V.
OIL TEMP 68F

--J1708 DATA--
 
 ERROR:
J1708 NOT READING.

Turn on ignition key to run transfer 

of data.

The vehicles data will appear. Much 

of the information accessed, such as 

the oil temperature will be used in the 

calculation of the test results. Press 

(Y Enter).

J1708 DATA

Select J1708 Data from 

the main menu. You will need 

to press (-Down) to scroll to the 

selection. The arrows to the right 

indicate directions they can be 

scrolled. Press (Y Enter) to make 

the selection.

If  ERROR appears the connections 

has not been established.

15

15

Summary of Contents for BVA-2100

Page 1: ...t measures the voltage drop of the starting and charging circuit The BVA 2100 is automated and menu driven with simple hook up methods for testing the negative and positive legs Special tests are incl...

Page 2: ...ing Fan Load Clamps 10 ft 6 Gauge External Leads 20ft 16 Gauge Size 9 5 X 12 X 13 Post Adapter Kit For group 31 batteries Optional AC 25 6 pin to 9 pin J1708 Adapter Optional AC 26 J1708 Cable Optiona...

Page 3: ...ernator Test Results 19 Using the Amp Probe 20 7 Starting System Test 21 28 8 Magnetic Circuit Test 22 24 9 Starting Cable VDrop Test 25 26 10 Individual Starter DrawTest 27 Starter Test Results 28 11...

Page 4: ...gradually build up and crystallize on the plates greatly reducing the battery s capacity and ability to be recharged n Cycling Excessive drain on battery when alternator is not operating CAUSE OF BAT...

Page 5: ...to the consumer when determined by the manufacturer that the product failed due to defects in material or workmanship This warranty is limited to the repair or replacement of parts and the necessary...

Page 6: ...load in each test Jaw insulation is necessary for accurate readings Damaged clamps or loose wires will affect the readings Keep clamps clean and in good repair DO NOT ATTEMPT TO REPLACE CLAMPS WITH A...

Page 7: ...is 1 0 Volts Maximum drop at 80 Amps is 1 0 Volts Maximum drop at 40 Amps is 2 0 Volts Reports the drops at the entered current Reports the drops at the entered current 24 Volt 12 Volt 24 Volt 12 Vol...

Page 8: ...A to M and 01 00 for the day and the year You have to increment each of these to the desired date that will print out in the standard 00 00 format Select MARGINAL BATTERY to allow the test result to b...

Page 9: ...nsfer Menu then select Stop n Launch Microsoft Excel and select open file n Under Files of Type at the bottom of the open file window select All Files n Highlight your download txt file then select Op...

Page 10: ...PM service NOT when the vehicle is having electrical system issues For a vehicle with a suspected electrical problem use the individual tests starting with the batteries then the cables and finally t...

Page 11: ...al port and you re planning on using Windows HYPER Terminal as illustrated below you will need to buy and install an adapter card with a serial port 11 11 BATTERY BANK TEST 2 You will be asked if the...

Page 12: ...ructed to connect the large leads Connect the red clamp to the main positive cable coming to the bank and the black clamp to the main negative cable leaving the bank Using the or key adjust the CCA of...

Page 13: ...ers on threaded steel posts as illustrated on the next page then press Y Enter When the test results appear as GOOD BATTERIES after running the system battery bank test there is no need to run the ind...

Page 14: ...ng help selection will be listed adding valuable information not necessarily in manul GENERAL INFORMATION SYSTEM TESTING BATTERY TESTING VOLTAGE DROP TESTING CHARGING CABLES VDROP TESTING MAG CIRCUIT...

Page 15: ...test and the alternator test MAIN MENU BATTERY BANK TEST VDROP MENU ALTERNATOR TEST STARTER DRAW TEST REVIEW PRINT MULTIMETERS J1708 DATA J1708 DATA ATTACH J1708 DATA CABLE N TO CANCEL J1708 DATA TURN...

Page 16: ...xternal leads will check the cables before the alternator is tested This is the individual VDorp Test ALTERNATOR HOOKUP Red to Positive Black to Ground BATTERY HOOKUP Black Clamp at Negative Main Red...

Page 17: ...LOADING PLEASE WAIT 27 CHARGE CABLES 01 07 13 11 55AM PASSED AT 120A GOOD UP TO 185A POS DROP 0 18V NEG DROP 0 16V If all connections are correct press y Enter to begin VDrop Test Wait for a load to b...

Page 18: ...nter the alternator rating Press Up or Down key to increment or decrement to the desired test The last 150 tests are held in memory The same tests can be downloaded to a PC See the Download section fo...

Page 19: ...f the cables Both the positive and negative circuit results will be indicated from the single test Select LIFTGATE CHARGE LIFTGATE MOTOR or LIFTGATE TRUCK CIR to perform a voltage drop test on the tra...

Page 20: ...Alternator and the Starter Draw Test whether they are individual tests or within each of the system tests The Amp Probe can also be used in the Multimeters test This section explainsthe proper use of...

Page 21: ...URRENT 640A CRANK TIME 2 24S 218 12V STARTER 07 05 12 05 52PM BEG VOLTS 12 56 END VOLTS 9 48 CURRENT 860A CRANK TIME 1 68S If still out of specifications High Amp reading may indicate engine is out of...

Page 22: ...self The Magnetic switch is energized by the ignition switch in each test For safety disconnect the negative cable from the battery while making the connections INDIVIDUAL MAGNETIC CIRCUIT TEST 8 VDRO...

Page 23: ...ction from the battery press enter and energize the switch again for 3 5 seconds See Illustration small clamp position 2 INDIVIDUAL MAGNETIC CIRCUIT TEST Cont 23 23 MAIN CABLES CONNECT LARGE LEADS TO...

Page 24: ...R Y Does the vehicle have a split battery system This entry is necessary for the tester to calculate 1 2 for each system if selected 9 STARTING SYSTEM VDROP TEST Loose or corroded terminal connections...