19.

 

DOOR ALIGNMENT 

Adjustment holes have been predrilled in the 
top track.  Door alignment can be achieved by 
using 4mm hex key through the top track into 
the top of the door hangers.  Turn the key 
anticlockwise to lift the door.   

 

20.

 

HANDLE INSTALLATION 

Assemble the handles as shown. Clear gaskets 
are supplied with 
the handle.  
Position one on 
each side 
between the 
glass and handle. 

 

 

 

* The stainless steel handle assembly is optional 

21.

 

SILL INFILL

 

Trim the sill infill to fit between the fixed panel 
and the return panel. Apply a continuous bead 
of clear silicon to each inside face of the base 
channel and at each end. Ensure the ends of the 
sill infill are 
completely 
filled and 
place the infill 
into the base 
channel in the 
location as 
shown.

 

 
 
 

22.

 

SLIDING DOOR GUIDE BLOCK

 

E

nsure the guide block isn’t too tight (must 

allow the glass to slide through it).  Slide the 
door as far back in an open position as possible. 
Slip the sliding guide block under the door and 
locate it in line with the end of the fixed panel 
on the opening side. Apply a small bead of 
silicon to the bottom and side of the block and 
then place into position 

 firmly to the inside of 

the glazing channel. Use a 1 or 2mm packer on 
the outside of the glass to firmly press the glass 
against the guide block.   Tape glass and block 
into place to ensure they do not move while 
silicon cures. 
 

23.

 

CLEAR FLEXIBLE WEDGE 

2x lengths of clear flexible wedge have been 
supplied.  Wedge can be inserted into wall 
channel, outside of glass panel. This will hold 
panel in position, prior to final silicone seal.  
These are to be used at installer discretion. 

Wedge is 

not

 to be used in base channel.  

Base channel and glass junction is to be 
siliconed as per below.

 

 

24.

 

SILICON APPLICATION 

Using the blue tape supplied, mask the glazing 
channels and glass at the intersections as 
shown. Apply clear silicon to the inside and 
outside of 
the base 
and wall 
receiver 
channels. 
Use a 
spatula to 
remove the excess silicon. Remove the masking 
tape immediately after application.  
 
 
 
 
 
 

Summary of Contents for miGLIDE MG2-SMALL

Page 1: ...asure 1x Bag11 Packers Phillips Screwdriver 1x Blue Masking Tape 1x BAG GB G sliding door guide blocks 1 x Clear Silicon 1 x BAG MG SCREWS 8x6 x10CSK screws 2x6 x40CSK screws 2 5mm drill bit 2 x Clear...

Page 2: ...efect must be visible to the naked eye in normal daylight conditions standing at a distance of two meters Any imperfection that is not visible within the above noted parameters will not be accepted by...

Page 3: ...hannels Use a straight edge and mark the wall to indicate where the wall channel is plumb 5 Apply a silicon bead to the full length of channels Silicon used must be compatible with anodised aluminium...

Page 4: ...wall channel 11 INSTALLATION OF THE RETURN PANEL Locate the glass panel 20 B into the glazing channel Adjust height of panel if necessary by adding or removing plastic packers bag11 in the base glazi...

Page 5: ...4x 6 x10CSK screws Fixed Panel this end 17 END CONNECTOR ANGLE MG 2W Fix the MG 2W end connector angle into place Screws should be left slightly loose 18 TOP TRACK AND DOOR PLACEMENT Stand inside the...

Page 6: ...the door as far back in an open position as possible Slip the sliding guide block under the door and locate it in line with the end of the fixed panel on the opening side Apply a small bead of silicon...

Page 7: ...d colour finish Install into the recess into the top track Sand the reverse face of the acrylic to allow for adhesion Apply 2 x 3mm beads of silicone to front face of top track Place the detail strip...

Page 8: ...1909 Revision By JST ACRYLIC LINER Z FLASHING When a 2mm Acrylic Wall liner has been supplied the aluminium Z Flashing will need to be trimmed Using a hacksaw trim the inside angle of the Z flashing a...

Page 9: ...nstalled on base prior to tiling Black Pearl Installed onto acrylic base when installing screens CODE ABS LQ GB SHORT Linea Quattro Installed after tiling or on an Architectural Finish when installing...