Any revisions must first be approved by the product designer.  Version: 201909 

Revision By:  JST 

 

14.

 

When the idle rollers are being fitted to hangers 
apply a 5mm drop of clear silicone inside the 
thread.  This will ensure that the hanger does 
not move out of adjustment.

 

 

 
 
 
 
 
 
 
 
 
 
 
 

15.

 

TOP TRACK

 

Slide the idle rollers into 
the top track as per 
diagram. 
   

 

 
 
 
 
 
 
 
 

16.

 

END CONNECTOR MG-3W

 

Fix MG-3W end connector bracket flush with the 
end of the top track using supplied 4x 6#x10CSK

 

screws. 
 

 
 
 
 
 
Fixed  
Panel 
this end 
 
 
 

 
 
 
 
 

17.

 

END CONNECTOR ANGLE (MG-2W)

 

Fix the MG-2W end connector angle into place. 
Screws should be left 
slightly loose.   
 

 
 
 
 
 
 
 

18.

 

TOP TRACK AND DOOR PLACEMENT

 

Stand inside the 
shower and 
manouver the 
pre-assembled 
door and top 
track inside the 
shower.  
Carefully lift the 
top track with 
the door 
attached into place over the return panel 

20 

MGF.

 The top track will sit on the wall channel 

on the fixed panel side and the MG-2W end 
connector angle will slide over the glass return 
panel.  Ensure the top track is level.  Fix the MG-
3W end connector bracket to the wall.  Tighten 
the screws into the end connector angle firmly.

 

 
 

 
 
 
 
 
 
 

Summary of Contents for miGLIDE MG2-SMALL

Page 1: ...asure 1x Bag11 Packers Phillips Screwdriver 1x Blue Masking Tape 1x BAG GB G sliding door guide blocks 1 x Clear Silicon 1 x BAG MG SCREWS 8x6 x10CSK screws 2x6 x40CSK screws 2 5mm drill bit 2 x Clear...

Page 2: ...efect must be visible to the naked eye in normal daylight conditions standing at a distance of two meters Any imperfection that is not visible within the above noted parameters will not be accepted by...

Page 3: ...hannels Use a straight edge and mark the wall to indicate where the wall channel is plumb 5 Apply a silicon bead to the full length of channels Silicon used must be compatible with anodised aluminium...

Page 4: ...wall channel 11 INSTALLATION OF THE RETURN PANEL Locate the glass panel 20 B into the glazing channel Adjust height of panel if necessary by adding or removing plastic packers bag11 in the base glazi...

Page 5: ...4x 6 x10CSK screws Fixed Panel this end 17 END CONNECTOR ANGLE MG 2W Fix the MG 2W end connector angle into place Screws should be left slightly loose 18 TOP TRACK AND DOOR PLACEMENT Stand inside the...

Page 6: ...the door as far back in an open position as possible Slip the sliding guide block under the door and locate it in line with the end of the fixed panel on the opening side Apply a small bead of silicon...

Page 7: ...d colour finish Install into the recess into the top track Sand the reverse face of the acrylic to allow for adhesion Apply 2 x 3mm beads of silicone to front face of top track Place the detail strip...

Page 8: ...1909 Revision By JST ACRYLIC LINER Z FLASHING When a 2mm Acrylic Wall liner has been supplied the aluminium Z Flashing will need to be trimmed Using a hacksaw trim the inside angle of the Z flashing a...

Page 9: ...nstalled on base prior to tiling Black Pearl Installed onto acrylic base when installing screens CODE ABS LQ GB SHORT Linea Quattro Installed after tiling or on an Architectural Finish when installing...

Reviews: