MANDATORY INSTALL REPORT CHECKLIST
Attention: Installer - upon Commissioning;
This Form must be completed and handed to the
Builder or Householder.
The Installer is responsible for Commissioning & Testing
-
For “Yes”, x for “No”.
Has the installation been installed in accordance with Workplace Health & Safety regulations?
Is the Contractor Solar accredited?
Has this system been installed to Australian standards AS3500.4
–1994 and Wiring Rules
AS/NZS 3000?
Has the contractor located the solar collectors where site drawing or order nominates?
(Collectors should be facing North for optimum efficiency).
Has the system been installed as per this
“Installation Instructions and Owner’s Manual”?
Has there been a 500kPa Pressure reducing valve installed?
Have all supplied Valves, Fittings & Protection Boots been fitted?
Have both Solar Collector sensor & Tank sensor leads been installed and TESTED to ensure
they are functioning correctly?
Have both the Flow & Return COPPER pipes been correctly insulated; Armorflex 13mm (or
similar)?
Does the pump light switch on when operating?
Is either the Panel sensor Light or Tank sensor Light illuminated or flashing at any time?
Are the Solar Flow & Return lines installed using Copper pipe? (Plastic Pipe or similar not
acceptable)
In areas where frost or freezing (below 5°C) is prevalent are FROST PROTECTION VALVES
fitted?
If installed where Frost is prevalent ensure that no form of booster isolation switch has been
installed.
Has the Air been purged from system?
Has the circulation pump been tested to ensure water is circulating to and from the solar
collectors?
Have wires from the tank been connected in the meter box?
Prior to leaving site have all joins & fittings been checked for leaks?