background image

AquaBreak Series  

Page 

13

 of 

18

 

AquaTech-Pressmain Instruction Manual\AquaBreak 

 

2.2 

COMMISSIONING 

 

The unit should only be commissioned by a competent person; 

A competent person is someone who is technically 

competent and familiar with safety practices and the hazards involved

 

2.2.1 

READ GENERAL SAFETY INFORMATION 0.0, WARNINGS 0.1 and CAUTIONS 0.2, 0.3 & 0.4. plus the 
additional warnings and cautions 1.1 & 1.2 

2.2.2 

This pumpset has been tested in the factory prior to delivery. However, it is impossible to simulate the 
actual on‐site conditions, especially if they are unusual. Therefore we can (if required) 

commissioned 

the pumpset 

, make any necessary adjustments and leave the set in operational order. Please see 

contact information at the end of this manual. 

2.2.3 

Should you wish to commission the pumpset yourself, then please follow the instructions below: You 
must ensure that; 

2.2.3.1 

the equipment has been correctly installed; 

2.2.3.2 

a written scheme of examination has been obtained where required under the Pressure Systems 
Safety Regulations; 

2.2.3.3 

any necessary chlorination or other treatment has been completed; 

2.2.3.4 

the system pipework has been thoroughly flushed prior to final connection of the pumpset to ensure 
any contaminants/chemical residues and foreign particles have been completely removed; 

2.2.3.5 

an adequate water supply (1 to 3Bar) and permanent electricity supply (230vac 1 phase 50Hz 6 Amp) 
are available; 

2.2.3.6 

the pipework etc in the building being served by the pumpset is capable of accepting the generated 
pressures. 

2.2.4

 

with the power and water OFF, check tightness of all mechanical and electrical connections, to ensure 
they have not loosened during transit. 

2.2.5

 

with the pumpset switched off (IS1) and the motor circuit breaker switched off (CB1), close the 
discharge isolating valve. 

2.2.6 

close the mains water inlet isolating valve, check and clean the strainer, re‐install strainer ensuring it is 
leak free. 

2.2.7

 

check the control vessel air charge is correct (1.3Bar) when there is no pressure on the discharge. 

2.2.8 

check and clean pump suction strainer/inlet filter (See Fig 2.1) 

 

2.2.9 

slowly open mains water inlet valve, switch on unit to allow solenoid valve to open and fill the mains 
water break tank. 

2.2.10

 

ensure the pump is primed (filled with water) before starting otherwise the pump seal will be 
damaged and cause it to leak (see fig 1.1a). 

2.2.11

 

once the pump is fully primed, switch the pump motor circuit breaker (CB1) on and allow the pump to 
pressurise against the closed discharge valve. The pump should stop when closed valve pressure has 
been achieved (plus a short run on time). 

2.2.12

 

ensure all system outlets are closed, SLOWLY open the pumpset discharge valve to allow the pump to 
pressurise the system pipework. Check for leaks and repair them. 

2.2.13

 

open and close each system outlet in turn allowing water to flow from each outlet until all the air is 
purged. As each outlet is opened and closed the pump should start and stop (stops after a short time 
delay). 

2.2.14

 

if any outlet on the system is opened and closed this should cause the pump to start and stop and the 
breaktank to refill as necessary. If this is so then the pumpset is working normally. 

2.2.15

 

check for normal operation and that no leaks are present, check all isolation valves on the pumpset 
are open and all covers are fixed in place before leaving the installation unattended. 

 
 

 

Summary of Contents for AquaBreak AB5

Page 1: ...BREAKTANK PUMPSET FOR BACKFLOW PROTECTION TO FLUID CATEGORY 5 ISSUE 3 18 07 2017 Head Office AGM House London Rd Copford Colchester Essex CO6 1GT UK Tel 01206 215121 Email aftersales agm plc co uk Man...

Page 2: ...NANCE 6 1 INSTALLATION INSTRUCTIONS 7 1 1 ADDITIONAL WARNINGS 7 1 2 ADDITIONAL CAUTIONS 7 1 3 PROCEDURE 7 1 3 1 OFF LOADING AT SITE 7 1 3 2 LOCATION 8 1 3 3 FIXING 8 1 3 4 PIPEWORK 9 1 3 5 FLOW THROUG...

Page 3: ...ions PSSR and the Owner User should be made aware of their responsibility for this see section 3 Servicing Failure to install operate use maintain the equipment as recommended below could cause damage...

Page 4: ...it will contain under worst case fault conditions E g fully saturated pressure vessel with no air charge break tank full to overflowing etc Failure to observe this could cause serious mechanical dama...

Page 5: ...accumulators 0 2 15 It is the installers responsibility to ensure subsequent pipework etc can accept the pressures generated by the equipment pumpset and to install an overpressure safety device into...

Page 6: ...nning causing pump seal damage and water leakage 0 3 8 Do no attempt to start pumps without liquid in volutes pumps must be fully primed see 1 2 2 mechanical seals must have a film of liquid between f...

Page 7: ...pplied as loose item is installed in the breaktank overflow warning pipe see fig 1 3 1 2 4 Mains water pressure to unit should be between 1 0 and 3 0Bar Ensure a pressure reducing valve set at a maxim...

Page 8: ...a minimum distance of 500mm all round There must be sufficient room to fully open panel door lift and withdraw pumps withdraw diaphragms from vessels Any Hydraulic Accumulator supplied should be loca...

Page 9: ...it an extra non return valve to the discharge as it may interfere with the correct operation of the non return valve already fitted as standard in the pumpset 1 3 4 5 Connect site pipework to mains wa...

Page 10: ...ure to the correct level see section 2 4 dependent on the application required for the vessel Refer to the Operating parameters at the back of this manual or contact Aquatech Pressmain for advice 1 3...

Page 11: ...eak Tank Stop Start Filling Solenoid Probes B3 B2 B1 B2 B3 B1 Level Control Relay set to FS filling short delay medium sensitivity 75k range 5k 150k Solenoid Valve n c min com max SV1 LR1 A1 A1 14 14...

Page 12: ...authorised AquaTech Pressmain agent This Assurance does not apply to those items not supplied by us or to defects arising from parts not made or approved by AquaTech Pressmain The individual manufactu...

Page 13: ...ss of all mechanical and electrical connections to ensure they have not loosened during transit 2 2 5 with the pumpset switched off IS1 and the motor circuit breaker switched off CB1 close the dischar...

Page 14: ...all or floor mounted 2 3 3 1 For normal operation all pumpset inlet and discharge valves should be left open all hydraulic accumulator expansion vessel isolating valves should be left open and drain c...

Page 15: ...onds and switch power on again to reset control relay No water pump does run Pump air locked Vent prime pump to remove all air Check pump suction strainer inlet filter Reduced intermittent flow Pump p...

Page 16: ...any build up of debris Fig 2 1 Pump inlet filter suction strainer Mains water inlet strainer The mains water inlet strainer should be regularly checked to remove any build up of debris Fig 2 2 Mains w...

Page 17: ...s Its specialist fields are Pressure booster equipment and sealed systems for heating and chilled water distribution systems Regular servicing of any plant for essential services is vital because wear...

Page 18: ...ter Essex CO6 1GT UK Telephone 01206 215121 OPERATING PARAMETERS SERIAL No MODEL AB5 THE SERIAL MODEL NUMBERS MUST BE QUOTED WHEN REQUESTING ASSISTANCE ELECTRICAL DATA Supply 230 volts 1 Ph 50 Hz Full...

Reviews: