background image

Australian Pipeline Valve - Installation, Operation and Maintenance Manual

9

FLOATING BALL VALVES - BV100 SERIES

temperature. It will be the responsibility of the operator to ensure valves are kept cool during welding 
and then post-weld testing of the valve should be performed. Larger size valves over 80 NB (3”) are less 
likely to transmit heat to seat and stem packing during welding but still care should be taken. The ‘swing 
out’ version of BV100 Series valve can be disassembled prior to welding to avoid damage to seats and 
body seals (only 3 bolts need to be removed to ‘swing out’ the centre section of the remaining bolt). 
Ensure the centre section of the valve is ‘swing out’, typically only 800 class up to 50 NB (2”) are ‘swing 
out’ design. The seats and seals remain in the centre section hence no seat or seal removal is required. If 
this option is recommended by APV then these valves have in-line removable sections hence no line 
movement is necessary to insert the fully self contained centre section. There must be sufficient 
movement in line to allow tightening of body bolts to compress the body gasket. In class 1500 and 2500 
the disassembly method cannot be performed due to intersecting components.
1- Tack weld in 4 points on both end caps, leave the valve in the open position and do not move during 

and at least 30 minutes after welding until the valve cools. For socket weld also see 2.3.3, for butt 
weld also see 2.3.4.

2- Remove centre section and complete welding.
3- Replace centre section but first apply grease to the seat rings to aid the seat and torque (unless for 

oxygen service).

The below procedures should also be followed:
a) Always ensure there is no pressure or product in the line. Ball valves will be supplied with socket weld 

ends to ANSI B16.11 or butt weld ends to ANSI B16.25. Welding should be done using procedures and 
welders qualified under section IX of the ASME boiler and pressure vessel code.

b) For 1500 & 2500 class valves, if the body seats are removed, put them back in the same side from 

which they were removed and take care not to cut or scratch them. Smear some grease into the seat 
pocket to help them fit into pockets. (Don’t apply grease if for oxygen service). If the valve leaks from 
the stem after assembly, try adjusting the stem packing. Always clean all welding surfaces from 
contamination, grease etc., prior to welding.

Note: For higher pressures and sizes, Delrin and PEEK seats may have graphite or PTFE backing rings.
c) Always do as a low temperature weld as necessary to obtain a reliable connection. Use whatever 

measure necessary to localise heat at the joint, dissipating it before damage can occur to adaptor 
gaskets and/or seats (the main risk is seats). Use a tempil stick or other temperature indicator on the 
outside of the valve body (centre section) directly adjacent to adapter end piece) being welded to 
assure the body temperature does not increase 160°C. Always leave valve in open position during 
welding but also at least 60 minutes after welding unit valve cools.

d) Where required APV will supply spare body gaskets. Graphite body gaskets are brittle so great care 

should be taken not to damage.

2.4.2 No Disassembly Method

Valves under 50 NB (2”) that are not disassembled should have pup ends fitted to avoid seat damage. If 
not fitted ensure valve body temperature is kept cool. Temperatures over 180°C can damage seats & 
seals. In 1500 and 2500 class, BV100 valves have encapsulated seats, hence you must have 3mm of 
movement in your line in order to replace disassembled centre section, due to seats intersecting end cap 

Summary of Contents for BV100 Series

Page 1: ...www australianpipelinevalve com au INSTALLATION OPERATION MAINTENANCE MANUAL FLOATING BALL VALVES BV100 SERIES...

Page 2: ...et Oilfield Products Valves Wellheads Gate Globe Check Valves Forged Steel Plug Valves Lubricated Sleeved Lined Gate Globe Check Valves Cast Steel Diamond Gear Gearboxes Flowturn Gate Globe Check Valv...

Page 3: ...llation positions 7 2 2 Preparation for installation 7 2 3 End connections 7 8 2 4 Valve installation by welding 8 10 3 0 Operation 10 3 1 Manual operation 10 3 2 Lock device 10 4 0 Maintenance 10 15...

Page 4: ...sponsible for ordering the correct valves The user is responsible for ensuring APV Valves are selected and installed in conformance with the current pressure rating and design temperature requirements...

Page 5: ...ct inside the valve 8 Australian Pipeline Valve Standard ball valves are not suitable for low temperature service below 29 C 20 F unless provided with cryogenic stem extension and other modifications...

Page 6: ...re Valve surface temperature may be dangerously too hot or too cold for skin contact Upon disassembly attention should be paid to the possibility of releasing dangerous and or ignitable accumulated fl...

Page 7: ...and Class 600 flanges or with buttweld ends 1 1 ENVIRONMENTAL CONSIDERATIONS According to ISO 14000 regulations and the environmental policy of APV the recyclability of the components that form part...

Page 8: ...o reduce mechanical loading on end connections Never use the lever wrench to hold the valve during transport handling or assembly The following procedure is required to be followed for correct install...

Page 9: ...nd to be operated Ensure sufficient clearance for the stem in the full open position Inadequate clearance for valves may add mechanical loading to the valve ends Sufficient clearance should be allowed...

Page 10: ...e temperature measurement strip must be monitored constantly throughout the welding work If any change of colour is noticed the welding work must be interrupted immediately and the weld allowed to coo...

Page 11: ...ct in the line Ball valves will be supplied with socket weld ends to ANSI B16 11 or butt weld ends to ANSI B16 25 Welding should be done using procedures and welders qualified under section IX of the...

Page 12: ...elding Refer to ASME B31 1 B31 3 etc Written welding procedures covering all attributes of the process and materials to be welded shall be in accordance with Section IX of the ASME Boiler and Pressure...

Page 13: ...If leakage cannot be halted by adjusting packing repacking of the valve is indicated Refer to field repair Do not attempt to replacing packing or replace stem while the valve is in service The stem i...

Page 14: ...ring However these parts can only be replaced during complete disassembly of the valve If a PTFE stem o ring is fitted it can be replaced with an elastomer o ring suitable for the service medium and t...

Page 15: ...e valve in the half open position and remove all pressure and drain the system Make sure that leakage of any residual material is caught in an appropriate container and disposed of properly 2 For gear...

Page 16: ...ain clean valve including contents in cavity 2 Remove 2 BOLTS from 1 BODY and 4 CAPS 3 Take off 4 CAPS from 1 BODY and remove 5 GASKET 4 Carefully remove 15 BALL Avoid scratching BALL surface 5 Remove...

Page 17: ...is dirt 3 The times of on off operation are too many or dirt exists on the surface of the ball 1 Loosen nuts and adjust again 2 Pull apart the valve and clean the dirt Ball Seat Leaking 1 Valve not fu...

Page 18: ...SS SS Galv SS SS Galv 11 Stem Nut SS304 SS304 A20 SS304 12 Stem A276 316 A276 316 B437 A20 B437 A20 13 Cover Plastic Plastic Plastic Plastic 14 Stop Pin SS304 SS304 A20 SS304 15 Ball A276 316 A276 316...

Page 19: ...re based on 30 000 psi 206 85 Mpa bolting stress and lubricated with heavy graphite and oil mixture or a copper based anti seize grease 6 Do not exceed by more than 25 of values stated when emergency...

Page 20: ...body bolts with system de pressurised and gland packing bolting is permissible if leakage occurs in these areas Required Torque values are given in Table 1 The use of copper based Anti seize grease f...

Page 21: ...351 CF8M 316 RPTFE GRAPHITE PTFE GRAPHITE PTFE GRAPHITE AISI 304 AISI 301 ASTM A276 316 AISI 304 AISI 304 AISI 304 ASTM A193 B8 1 2 3 3 SET 4 PTFE 3 OUTER INNER SOLID 3 15 16 17 18 HANDLE SLEEVE PACKI...

Page 22: ...Australian Pipeline Valve Installation Operation and Maintenance Manual NOTES...

Page 23: ...hures and technical publications are the exclusive property of Australian Pipeline Valve Any unauthorised reproduction in total or in part shall result in prosecution Products and data sheets in this...

Page 24: ...e contact us for a prompt response Continuous development of Australian Pipeline Valve products may necessitate changes in the design or manufacture process Australian Pipeline Valve reserves the righ...

Reviews: