ALTENERGY POWER SYSTEM, INC.
11
Installation Procedures
WARNING:
Do NOT connect APS Micro-inverters to the utility grid or energize
the AC circuit until you have completed all of the installation procedures as
described in the following sections.
For bracket installation, after the completion of system installation rendering as follows:
Step 1 - Installing the AC Branch Circuit Junction Box
a.
Install an appropriate junction box at a suitable location on the PV racking system
(typically at the end of a branch of modules).
b.
Connect the open wire end of the AC branch end cable into the junction box using an
appropriate gland or strain relief fitting.
c.
Wire the conductors: L- BROWN; N – LIGHT BLUE; PE –YELLOW/GREEN.
d.
Connect the AC branch circuit junction box to the point of utility interconnection.
NOTE
: Be sure to size the AC wire to account for voltage drop between the
AC branch circuit junction box and the point of utility interconnection. Refer
to the tables below.
Go to distribution box