The Force Dual Phase™ Operation Manual
14
Revision Date: 4/22/2019
2.7.3.
Close the vessel by placing the plug back into the nut and rotating until the safety
closure pinhole is in the correct location.
Figure 15. Closing Vessel
2.7.4.
Insert safety closure pin and reattach flexible CO
2
hose, as shown in Figure 16.
Figure 16. Appearance of closed and reconnected vessel
2.8.
Chiller Start Up
2.8.1.
Verify that both chillers’ cooling lines are connected to the extraction system.
2.8.2.
Turn chiller on.
2.8.2.1. The main power switch is located on the back of the chiller.
2.8.2.2. The operation power button is located to the left of the display on the front.
2.8.3.
Set the target temperature that corresponds with each coolant loop in the system.
Target temperatures can be found in recommended operating parameters section.
Rotate 30 degrees until holes line up