Pitched roof mount installation manual – Version 2016 1.0 to AS/NZS1170.2.2011 Amdt 3
–
2012 12
Note: If necessary, use an angle
grinder or hammer to cut a concavity
in the tile that covers the roof hook
at the point where the roof hook
comes through. (Caution! Must not
use fixed roof hook as a ladder, as
this extreme point load could
damage the tile below.
9. Place the solar module on the
rails, slide the end clamp tightly
against the solar module and fasten
tightly using the Allen bolt
(recommended torque is 8 Nm)
10. Slide the pre-assembled
inter-module clamp into the rails
from above, place it firmly against
the module and fasten loosely
(approx. 2-3 turns).
11. Now slide the next module
against the previously installed
module and tighten the inter-module
clamp using the Allen key, Take care
that the anti-slips protection sits in
the rail channel of the lowest row of
rails.