Commissioning
40
MAXXfl o EVO 150/302
5.1.2 FILLING THE CONDENSATE TRAPS
Before operating the burners it is fi rst necessary to ensure that both condensation traps are fi lled with water.
This is best done before the fi nal connection is made to the condensate drain. The following actions are sug-
gested:
1. Rotate the elbow of the condensate trap so that it is facing upward (see photo below).
2. If the condensate pipe is already installed, disconnect the elbow and move pipe away from conden-
sate trap (see photo below).
3. Pour approximately 500ml of water into the trap and replace / reposition pipes.
4. Proceed with the commissioning of the heat engines