M362500-01 Rev K
2-1
SECTION 2
INSTALLATION AND OPERATION
2.1
General
After unpacking, perform an initial inspection and function test to ensure that the unit is in good
working order. If the unit was damaged in shipment, notify the carrier immediately. Direct repair
problems to the Customer Service Department at 1-800-733-5427.
2.2
Initial Inspection
The equipment should be inspected for damage as follows:
•
Inspect for obvious signs of physical damage.
•
Turn front panel controls from stop to stop. Rotation should be smooth.
•
Test the action of the power switch. Switching action should be positive.
•
If internal damage is suspected, remove the cover and check for printed circuit board
and/or component damage. Reinstall cover.
2.3
Installation
2.3.1
Input Voltage Selection
Before using the DCS power supply, the correct AC input voltage must be selected and an
appropriate line cord and plug attached, or hook up wire sized for input current based on NEC
or local electrical code. The frequency of the AC input voltage must be maintained between 47
and 63 Hz.
All units are shipped in a configuration requiring a 200-250 Vac input. The unit can be con-
verted for use with a 100-130 Vac input or purchased preset for 115 Vac with the M1 Option.
CAUTION
Attempted operation of the DCS power supply with the incorrect input voltage may
result in internal damage to the unit.
For use with a
200-250 Vac input
, connect a 250 Vac 15 Amp rated plug and cord to the rear
panel AC connector and the safety ground screw. (Note that the NEUT. and LINE designations
above the AC connector do not apply to 200-250V operation.)