10.6.2 Emptying the hopper and/or metering unit and replacing the metering roller
1. Close the opening between the hopper and
the metering unit (only necessary when
hopper is full).
1.1 Remove the spanner (Fig. 240/1) from
the holder.
Fig. 240
1.2 Release two nuts (Fig. 241/1) but do
not remove.
Fig. 241
1.3 Turn the bolts (Fig. 242/1).
1.4 Push the shutter (Fig. 242/2) into the
metering unit up to the stop.