Installation Instructions [email protected] +1(909) 591-8431 www.alvaradomfg.com
Page 35
Yoke Installation (Cont)
6.
Using a " concrete drill bit, drill an anchor hole 3" in
depth (Figure A6). Repeat this step for the remaining
mounting holes.
NOTES
The anchor hole(s) must be clean before installing the
anchor bolt(s). If the hole(s) are not clear of debris, the
anchor bolt(s) may not tighten correctly.
7.
Insert one anchor into the drilled hole (Figure A6A). The
threaded end of the anchor must be inserted into the hole
rst. Use a hammer to tap the anchor into place, if
needed. Ensure that the anchor is ush with the
concrete oor.
8.
Place one lower mounting channel over a mounting hole.
Insert and tighten one
" x 2 �" HHCS bolt and
at washer.
Use a socket wrench and
16
9
" socket to tighten the bolts
(Figure A7). Repeat this step for the remaining lower
mounting channels and mounting hardware.
9.
Position the Yoke assemblies over the mounting channels.
Verify that the Yoke assemblies are ush with each other.
If the assemblies are ush with each other, then proceed to
Step 10. If they are not, remove the Yoke assemblies and re-
align the mounting channels.
10. Use a torque wrench and tighten the anchor bolts to 40 ft-lbs.
11. Place the Yoke assemblies over the mounting channels
12. Locate the two holes on the bottom of each Yoke assembly.
Secure each section to the mounting channel with a
�-20 x 1” screw (Figure
A8).
Once the Yoke is installed and secured, please proceed to the "OV
Installation" section.
Fig. A6
" Concrete
Anchor
” Concrete Drill Bit
A6A
Fig. A7
16
9
" Socket and
Socket Wrench
" x 2�" HHCS Bolt and
" Flat Washer
Mounting
Channel
Mounting Channel
Yoke Assembly
Mounting Channel
�-20 x 1” screw
Fig. A8
Yoke Installation (Cont)
Fig. A6
Fig. A8
A6A
6.
Using a ⅝" concrete drill bit, drill an anchor hole 3" in
depth (Figure A6). Repeat this step for the remaining
mounting holes.
NOTES
The anchor hole(s) must be clean before installing the anchor
bolt(s). If the hole(s) are not clear of debris, the anchor bolt(s)
may not tighten correctly.
7.
Insert one anchor into the drilled hole (Figure A6A). The
threaded end of the anchor must be inserted into the
hole first. Use a hammer to tap the anchor into place, if
needed. Ensure that the anchor is flush with the
concrete floor.
8.
Place one lower mounting channel over a mounting hole.
Insert and tighten one ⅜" x 2½" anchor bolt and at
washer. Use a socket wrench and 9/16" socket to tighten
the bolts (Figure A7). Repeat this step for the remaining
lower mounting channels and mounting hardware.
9.
Position the yoke assemblies over the mounting
channels. Verify that the yoke assemblies are flush with
each other. If the assemblies are flush with each other,
then proceed to Step 10. If they are not, remove the
yoke assemblies and realign the mounting channels.
10. Use a torque wrench and tighten the anchor bolts to
40 ft-lbs.
11. Place the yoke assemblies over the mounting channels
12. Locate the two holes on the bottom of each yoke
assembly. Secure each section to the mounting channel
with a ¼-20 x 1” screw (Figure A8).
Once the yoke is installed and secured, please proceed to the
"OV Installation" section.
⅝” Concrete Drill Bit
⅜" Concrete
Anchor
Yoke Assembly
Mounting Channel
Mounting Channel
¼-20 x 1" Screw
Mounting
Channel
⅜" x 2½" Anchor Bolt and
⅜" Flat Washer
9/16" Socket and
Socket Wrench
CPST Installation Instructions