24
Glazing Bar
Capping
610 x 1635
Glazing
9
There are 2 types of capping available on this range of
greenhouses. The standard cedar capping or the
upgrade aluminium capping.
If you have the Aluminium capping you need to slide
the glazing rubber into channels on the back of the
capping. Use a Stanley knife or scissors to cut to
length, it is best to use a complete length per side.
If you have the cedar capping you need to pre load
each strip with the 25mm screws. Also before you
install each pane you need to run a thin bead of silicon
up each glazing bar (no greater than 5mm is needed).
All of the capping is pre-cut to length, so sort through it
placing the capping around the building close to were
you can reach it. Start by glazing the first side section.
Make sure you have the first piece of capping to hand.
Glass Size 54
56
58 510 512
A
4 4 4 4 4
B
1 1 1 1 1
C
1 1 1 1 1
610x1635
4 6 8 11 13
610x938
3 5 6 7 8
610x868
1 1 1 2 2
610x153
1 1 1 2 2
525x100
6 12 12 12 12
610x305
1 1 2 3 4
610x610
1 1 2 3 4
558x908
1 1 1 1 1
457x1635
4 4 4 4 4
Slide the glass
into the rebate
of the eaves bar
and rest it on
the aluminium
base as above.
Side Cill
Glazing Bar
Side Base
Glass
Glazing Rubber
Silicone
Summary of Contents for Evolution Eight Series
Page 1: ...1 02 14...
Page 49: ...49 Notes...
Page 50: ...50 Notes...
Page 51: ...51 Notes...
Page 52: ...Helpline 0116 267 7091 www birstall com alton birstall com...