HYC_50
– Operation and Installation Guide
Hardware
Version 1-2
Page 34 of 76
4
HYC_50 Installation and commissioning
All rights reserved. Reproduction of this document, in whole or in part, is only permitted with the permission of alpitronic GmbH.
4.1.6. installation of the connection cable in the cable inlet
After the connection cable has been
stripped and the phases have been
roughly cut off, it can be fixed in the plastic
half-shell of the cable entry with the
installed cable bushing using the strain
relief (TX20).
Before this, the cable gland must be cut
off at the appropriate point for the cable
diameter using scissors/knives. During
installation, make sure that the sealing
contour follows the existing sealing
groove. The sealing cylinder points
inwards (see picture).
The individual strands must be cut and
stripped in the sections shown in the
figure, so that contacting is possible.
The length of the remaining insulation of
the cable, which is inside the cable entry,
must be selected so that the cable
bushing still seals on it.