HYC_50 Installation and commissioning
Page 27 of 76
All rights reserved. Reproduction of this document, in whole or in part, is only permitted with the permission of alpitronic GmbH.
4. HYC_50 Installation and commissioning
This chapter describes the mechanical assembly and electrical installation of the HYC_50.
It is recommended to assemble and install the HYC_50 according to the following steps:
-
Location selection (Chapter 4.1.3)
-
Positioning mounting frame HYC_50 (Chapter 4.1.4)
-
Connection area of the HYC_50 (Chapter 4.1.6)
4.1. Mechanical installation of the HYC_50
The following figure lists the relevant components for the mechanical installation:
Attention
Before installation, compliance with all legal requirements for the
installation site (e.g. tilt resistance, impact protection, frost exposure, etc.)
must be checked.
Each loading outlet must be as close as possible to the car park to be
served, taking into account ergonomics and mechanical impact
protection.
In Norway, charging stations for electric vehicles must be located far
enough away from a potentially explosive area so that charging cannot
take place within the potentially explosive area.
When selecting the installation height of the charging station, please
ensure that the plug holder of the charging station is at a height above
the ground in the range of 0.5 m to 1.5 m.
For barrier-free installation, the height specifications in Figure 15 must be
observed.
4.1.1. Mounting the Stand
The base of the HYC_50 can be fixed to the ground via 4 bolts M12 (see Figure 12). For this
purpose, own foundation bases are optionally offered.
However, the installation can also be carried out on any own foundation. The sufficient
mechanical strength of the foundation plate must be taken into account.