8.8

DHW EXPANSION VESSEL - See Fig. 8

Note: If a top rear flue has been fitted to the boiler, it may be necessary to loosen the flue connections to the boiler so as to
raise the height of the flue by approximately 10 mm to allow removal of the expansion vessel.

1.

Close the mains water inlet valve and ensure that all hot water taps are closed. Release the pressure from the hot water
circuit by opening and closing a hot tap which is lower than the store.

2.

Disconnect the expansion vessel union and for the CombiMax 600 remove the two screws securing the vessel to the right
side rear frame of the boiler.

3.

Remove the expansion vessel.

4.

Re-assemble in reverse order with a new vessel. Refill and pressurise the hot water circuit by opening the mains water
inlet valve.

8.9

DHW EXPANSION RELIEF VALVE - See CombiMax Schematic illustration

1.

Drain the CombiMax as described in section 8.2.

2.

Disconnect the valve pipework unions and remove the valve.

3.

Re-assemble in reverse order with a new valve.

4.

Refill the store (refer to Commissioning, section 5.1).

8.10 PRESSURE REDUCING VALVE FILTER/CARTRIDGE - See CombiMax Schematic illustration

1.

Close the mains water inlet valve and ensure that all hot water taps are closed. Release the pressure from the hot water
circuit by opening and closing a hot tap which is lower than the store.

2.

Unscrew the cartridge from the valve body.

3.

Clean or replace the filter/cartridge and re-assemble in reverse order.

4

Refill and pressurise the hot water circuit by opening the mains water inlet valve.

8.11 PRESSURE REDUCING VALVE/CHECK VALVE - See CombiMax Schematic illustration

1.

Drain the CombiMax as described in section 8.2.

2.

Disconnect the unions of the pipe between the water mains inlet valve and pressure reducing valve, and remove the pipe
from the manifold plate.

3.

Remove the pressure reducing valve/check valve.

4.

Re-assemble in reverse order with a new valve.

5.

Refill the store (refer to Commissioning, section 5.1).

8.12 BOILER FLOW CONTROL REGULATOR - See Fig. 9

1.

Drain the CombiMax as described in section 8.2.

2.

Refer to Fig. 9 and disconnect the pipework containing the regulator.

3.

Remove the regulator.

4.

Re-assemble in reverse order with a new regulator.

5.

Refill the store (refer to Commissioning, section 5.1).

8.13 DHW STORAGE CYLINDER - See CombiMax Schematic illustration

1.

Drain the CombiMax as described in section 8.2.

2.

Disconnect the DHW expansion vessel connection to the cylinder.

3.

Remove the DHW outlet thermostat as described in section 8.4.

4.

Remove the DHW temperature/pressure relief valve as described in section 8.6.

5.

Remove the DHW expansion relief valve as described in section 8.8.

6.

 Remove the DHW pump as described in section 8.3.

7.

Remove the pressure reducing valve as described in section 8.10.

8.

Remove the store thermostat as described in section 8.5.

9.

Disconnect all the pipework from the cylinder.

10. Cut and release the plastic security strap and lift the cylinder upwards to disengage it from the mounting frame. Pull the

cylinder forward and remove it.

11. Re-assemble in reverse order with a new cylinder, using new seals and new plastic security strap supplied.

12. Refill the store (refer to Commissioning, section 5.1).

Summary of Contents for Alpha CombiMax 350

Page 1: ...40 280 Range of Gas Fired Combination Boilers Building Regulations Certificate No ETC 03198 These instructions must be used in conjunction with the Installation instructions provided with the selected...

Page 2: ...te the hot water within the loop For full details contact Alpha Therm Ltd The CombiMax storage cylinder has the facility for fitting an electric immersion heater which must be obtained from Alpha Ther...

Page 3: ...r storage 50 C 350 model 600 model Reheat time for 70 of storage 350 model 600 model Min Clearances required for Servicing Top Bottom Sides Front Dimensions CombiMax Height 350 model Width 600 model W...

Page 4: ...r 5 DHW pump 6 Pressure reducing valve with filter and check valve 7 Drain point 8 DHW expansion relief valve 9 Store thermostat 10 DHW expansion vessel 11 Manual air vent 12 DHW temperature pressure...

Page 5: ...approximately 92 kg 350 model or 130 kg 600 model The CombiMax may be installed in any room or internal space although particular attention is drawn to the requirements of the current IEE WiringRegul...

Page 6: ...sistance created by each elbow or bend 0 8 m 1 0 m 1 4 m Maximum resistance allowed expressed as a length of straight pipe i e no elbows or bends up to 9 m up to 18 m up to 27 m Minimum size of discha...

Page 7: ...her with screws wall plugs and washers e Literature pack and DHW control knob label f Boiler conversion kit with restrictor spanner and boiler converted label 2 Unpack the boiler as per the Installati...

Page 8: ...Figs 5 and 6 as follows a Unscrew fitting A and discard the components A B and C as shown in Fig 5 Fig 5 Differential pressure sensor BEFORE modification b Screw fitting D supplied in the conversion...

Page 9: ...left hand side panel removed from the boiler to the CombiMax by hooking the top of the panel over the brown trim of the mounting frame and securing it at the bottom rear of the panel Secure the panel...

Page 10: ...ee Figs 9 and 10 and connect to the boiler terminal block via the grommet as shown in Fig 11 Refer to section 2 4 for connection details The boiler main terminal block can be removed by pulling it off...

Page 11: ...taps and allow water to flow until no air is present Turn off the taps Cover all electrical components beneath the CombiMax pump and then release the pump bleed screw until all the air has been vente...

Page 12: ...minutes and then the burner pressure will decrease slowly to its minimum until the hot water store reaches a temperature of approximately 56 C Check the burner pressure and that the burner goes out wh...

Page 13: ...biMax store Clean the filters within the pressure reducing valve and the mains water inlet valve 5 6 FINAL ASSEMBLY After completing the assembly of the boiler place the CombiMax front casing in posit...

Page 14: ...Refill the store refer to Commissioning section 5 1 8 4 DHW OUTLET THERMOSTAT See CombiMax Schematic illustration 1 Gain access as described in section 8 1 Ensure the electricity supply is isolated 2...

Page 15: ...water circuit by opening the mains water inlet valve 8 11 PRESSURE REDUCING VALVE CHECK VALVE See CombiMax Schematic illustration 1 Drain the CombiMax as described in section 8 2 2 Disconnect the unio...

Page 16: ...16 Alpha CombiMax 350 and 600 9 WIRING DIAGRAMS 9 1 COMBIMAX ILLUSTRATED WIRING DIAGRAM 9 2 COMBIMAX FUNCTIONAL FLOW WIRING DIAGRAM...

Page 17: ...stat TOD DHW expansion vessel 4 litre DHW expansion vessel 5 litre Temperature pressure relief valve 90 C 7 bar DHW outlet thermostat wax element Storage cylinder 35 litre Storage cylinder 60 litre Bo...

Page 18: ...mbiMax produced before February 1999 i e before Serial No A906 must not be fitted remote from the boiler 2 A CombiMax fitted remote has no casing Fig 13 Possible locations for the CombiMax in relation...

Page 19: ...IMUM CLEARANCES REQUIRED 12 5 WALL MOUNTING The wall mounting frame and security strap supplied are to be used to secure the CombiMax storage cylinder to the wall 12 6 CASING The casing components sup...

Page 20: ...er as shown in Fig 16 using 15 mm pipework The pipework supplied with the CombiMax can be utilised to provide the connections at the boiler and CombiMax 12 10 ELECTRICAL SUPPLY Connect the electrical...

Reviews: