4.3.2 Installation procedures
4.3.2.1
Get the battery ready
1.
Get the battery ready, ensure all the battery indicator is in OFF, and confirm whether the
appearance of the battery is normal;
2.
Confirm both the battery breaker and the system breaker that connected the battery with
inverter are disconnected.
3.
Turn on the signal switch of the battery, observe whether there is alarms on the panel,
measure it with multi-meter and record battery voltage, then check if it meets the parallel
standard: open circuit voltage difference < 0.5V;
4.
After confirming that everything is OK, turn off the battery and put it at the installation
preparation area for ready-to-install: