II/ Mounting the SolShare
A. Installation site selection
Do not mount the SolShare
on flammable wall material
Do not mount the SolShare near
flammable material or gases
Requirement for
installation space
90
˚
Mounted Vertically
90
˚
Mounted Vertically
Environmental boundaries
90
˚
Mounted Vertically
Max ambient
temperature:
50°C (+122°F)
Min ambient
temperature:
-10°C (-13°F)
Relative humidity:
0-90%
90
˚
Mounted Vertically
Mount vertically
Install in an easy to observe
and operate location
90
˚
Mounted Vertically
90
˚
Mounted Vertically
≈1200 mm
To minimise cabling required, the SolShare should be
mounted as close to the main switchboard (tenancy isolator
board) as possible.
To allow for easy installation and maintenance ensure that
there is adequate space surrounding the SolShare and
that it is mounted at a convenient height. Please ensure
the following mounting requirements are also met when
selecting the location of the SolShare.
Do not mount in direct sunlight
150 mm
150 mm
500 mm
500 mm
Pre-installment requirement
To do before mounting the bracket.
Screw in and lift up the antenna