Venting
A 4 inch diameter flue transition is factory installed on the
combustion air inducer outlet of all models.
Figure 16 shows
the combustion air inducer as shipped from the factory.
Mounting Screws Location
Figure 15
UPFLOW POSITION
Top Vent Discharge
Figure 16
The unit will not vent properly with the flue transition
pointed down in the 6 o’clock position.
The combustion air inducer may be rotated clockwise
or counterclockwise by 90° to allow for top or side vent
discharge in all applications. When the unit is installed,
the flue transition must be in the 9 o’clock, 12 o’clock or
3 o’clock position.
IMPORTANT
Figure 17
If necessary reposition the combustion air inducer, pressure
switch and/or make-up box as needed per the following
steps. See Figures 16 through 22.
1. Remove the four mounting screws (Figure 15) which
secure the combustion air inducer / pressure switch
assembly to the orifice plate. Lift the assembly and rotate it
90° clockwise or counter clockwise to either the 3 o’clock
position. Resecure with four secrews. Gasket should be
left in place.
2. Use tin snips to cut preferred opening on the cabinet for
repositioning the flue outlet. Use the cut-out piece as a cover
plate to patch unused opening on cabinet.
Figure 18
UPFLOW POSITION
Right Side Vent Discharge
•
Pressure switch tubing may be too long. Cut to fit, then reattach to barbed
fitting on pressure switch. Tubing must not be allowed to sag.
•
Remove make-up box assembly (2 screws) and cut wire tie to free make-
up box wires. Re install make-up box on other side of cabinet.
•
Resecure make-up box wires: Either pull excess wires through the blower
companrtment and secure using supplied wire tie, or coil excess wire and
secure to the gas manifold.
UPFLOW POSITION
Left Side Vent Discharge
Summary of Contents for 80G1UH
Page 3: ...506526 01 Page 3 of 39 Issue 1031 A80UH 80G1UH Expanded View Figure 1...
Page 27: ...506526 01 Page 27 of 39 Issue 1031 Wiring Diagram Figure 32...
Page 38: ...506526 01 Page 38 of 39 Issue 1031 START UP PERFORMANCE CHECK LIST UNIT SET UP...
Page 39: ...506526 01 Page 39 of 39 Issue 1031 UNIT OPERATION...