24
503806
For proper operation at altitudes above 2000 ft. (610 m) the natrual
gas valve spud orifice size must be reduced to ensure complete
combustion.
DO NOT connect the dryer to L.P. Gas Service without converting the
gas valve. A No. 458P3 L.P. Gas Conversion Kit must be installed by
the Manufacturer’s Authorized Dealers, Distributors, or local service
personnel.
L.P. gas service must be supplied at 10 ± 1.5 inch water column
pressure.
4.
If local codes allow the use of flexible tubing, connect the dryer to gas
line with new metal flexible tubing (use design American Gas
Association certified connector) to the 3/8 inch NPT (National Pipe
Thread) gas connection at the rear of the dryer (see below).
NOTE: When connecting to gas line, an equipment shutoff valve must
be installed within 6' (1.8 m) of the dryer. An 1/8 inch N.P.T. pipe plug
must be installed as shown. See illustration below.
Altitude
Orifice Size
Part
ft
m
#
Inches
mm
Number
2000
610
41
0.0960
2.44
503776
3000
915
42
0.0935
2.37
503777
5500
1680
43
0.0890
2.26
503778
7000
2135
44
0.0860
2.18
58719
9000
2745
45
0.0820
2.08
503779
10500
3200
46
0.0810
2.06
503780
D233IE2D
3/8" (9.5 mm) NPT
GAS CONNECTION
1/8" (3.1 mm) NPT
PIPE PLUG
(For checking
inlet gas pressure)
NEW METAL
FLEXIBLE
CONNECTOR
USE ONLY
IF ALLOWED
BY LOCAL
CODES
(Use
Design A.G.A.
Certified
Connector)
EQUIPMENT
SHUT-OFF
VALVE
Installed within
6" (1.8 m) of dryer