7
TMV3 ART 33 Screwed Rev 1
•
Temperature is in accordance with the valve application as per the table below: -
HP (1.0 – 5.0 Bar)
High Pressure
LP (0.2 – 1 Bar)
Low Pressure
Application
Maximum
Temperature (°C)
HP-B
LP-B
Bidet
38
HP-S
LP-S
Shower
41
HP-W
LP-W
Wash Basin
41
HP-T44
Bath
44
•
When the valve has been installed with the correct conditions of use it is advised that
the valve is subjected to normal operation prior to the commissioning at the application
temperature. Operate the valve from full cold to full hot at least three times by removing
the blue plastic cap and using a hexagon wrench to adjust.
•
With the valve at the full cold position bring the valve to the correct application
temperature by turning the nut clockwise. If the valve exceeds this temperature, return the
valve to the full cold condition, and reset it to the correct tempe0-2°C. Do not set a
valve with a lowered temperature as this will not provide consistent operation.
•
After adjustment replace the cap to lock the valve in position and prevent tampering.
•
Commissioning Test sequence
• After adjusting the temperature of the mixed water in accordance with the valve application.
•
Record the temperature of the hot and cold-water supplies.
•
Record the temperature of the mixed water at the largest draw-off flow rate.
•
Record the temperature of the mixed water at a smaller draw-off flow rate, which shall be
measured.
•
Isolate the cold-water supply to the mixing valve and monitor the mixed water temperature
recording the maximum temperature achieved and the final stabilized temperature.
•
Record the equipment, thermometer etc. used for the measurements.
•
The final stabilised temperature must not exceed the values in the table below and must
never exceed 46°C: -
Application
Max Temperature °C
Bidet
40
Shower
43
Wash Basin
43
Bath
46 (note 1)