PREPARING THE SLING BOLTS
ATTACHING THE DUCT CONNECTION FLANGES
INSTALLATION OF THE UNIT
Hang
the suspension braket on the anchor bolts
and adjust in such a way that the unit is installed
horizontally. Tighten up securely using double nuts in
order to prevent looseness.
If the duct
connection flanges are not
connected to the unit, use the screws that
can be found in the installation package to
connect the flanges to the unit as the figure
on the left.
Hang the unit
on the anchor bolts
and adjust in such a way that the unit
is installed horizontally. Tighten up
securely using double nuts in order
to prevent looseness.
WARNING
Check the stability of sling
bolts during the installation.
!
WARNING
Before attaching the duct
connection flanges, check that
no foreign matter has found.
!
WARNING
1 Connect the drainage line with downward slope.
2 Water condensed in the exchanger and coils should be
discharged by connecting the 1 pieces of ½” diameter drain
hose to the drain outlet under the unit.
3 The applications which can prevent the flow of water in the
drainage line should be avoided.
4 The drainage line shall never be moved to an upper level
than the drain pan.
!
Energy Box AC-A / AC
Series Unit
Anchor Bol
t
Nut
Washer
Rubber Isolator
Anchor Bolt (M10 or M12)
Nut
asher
Nut (kontra
)
Rubber Isolator