Page 37 of 83
SK2018 PCG(H)-V/P-AECM-001
B.14.
Mounting Front Panel Assembly
1.
Remove return grille from front panel.
2.
Move the front panel to the unit casing.
3.
Tighten 4 screws to attach the front panel as shown in Figure B.14.1 and Figure B.14.2. The front panel does not move
upwards excessively because the screws are not fully threaded (see below Figure B.14.3). Therefore, the height of false
ceiling and installation height should be measured accurately to ensure there is no gap between the false ceiling and the
front panel.
4.
Install the grille back to front panel.
Figure B.14.1
Figure B.14.2
Figure B.14.3
B.15.
Start-Up
The unit should not be started up until the system piping has been cleaned and all the air has been purged.
Check condensate drain pipe slope.
Confirm the condensate drain pump in good working order.
Confirm float switch is not loosen or become dislodged during shipping. Use the following steps to confirm pump
functionality:
1.
Install cassette unit in an absolute horizontal position.
2.
Fill the internal drain pan by pouring water through the external drain pan to confirm drain pump is working.
3.
Confirm flow of water through condensate drain pipe. If the water is not expelled, verify float switch is has not been
damaged.
4.
Verify air filter is clean and properly installed.