Photos 5a and 5b

 

– Measuring the Cable for 

Sizing Grommets

 
Note: Make sure that you are using the correct 
         set  of  grommets  and  applicable  Band-Mic  for 

either  the  Express  or  Drop  ports,  and  that  the 
initial measurements are correct. 

 

Photo 5a and Photo 5b - Measuring the Cable

for Sizing Grommet

 

 

8.02 

Position the grommet open and count the number 

of  layers  from  the  center  of  grommet  to  be 
removed.  Do  not  include  the  center  core  as  a 
layer. Carefully tear the layers from the grommet 
by using a pealing motion on the grommet. Refer 
to 

Photo  6a 

–  Counting  the  Grommet  Layers, 

Photo  6b

 

–  Tearing  the  Grommet  Layers  and 

Photo  6c

 

–  Grommet  with  Center  Core  and 

Layers Removed

.  

 
 
 
 
 
 
 
 
 

 
 

 

Photo 6a - Counting the Grommet Layers

 

 
 

 

Photo 6b - Tearing out the Grommet Layers

 

 
 

 

Photo 6c - Grommet with Center Plug and

Layers Removed

 

 
 
 
 
 
 
 
 

Summary of Contents for LG 250

Page 1: ...8mm Minimum Cable Diameter 0 30 7 6mm Maximum Cable Entry 5 ports Overall Dimensions ht x dia 19 X 8 75 438mm X 222mm 3 0 Contents 3 01 The LG 250 comes with materials to install five 5 cables into po...

Page 2: ...1 Cable entry should start with the selection of one or both of the Express Feeder ports first then with the Drop Lateral ports 5 02 The port closest to the center sections hanger attachment is used f...

Page 3: ...t bag Only remove the cable clamps and grommets from the ports to be occupied by cable Photo 4 Grommet Kit Contents 8 0 USING THE BAND MIC AND LAYER REMOVAL 8 01 Wrap the Band Mic around the cable in...

Page 4: ...2 Position the grommet open and count the number of layers from the center of grommet to be removed Do not include the center core as a layer Carefully tear the layers from the grommet by using a peal...

Page 5: ...arger flanges of the grommets fit in the first and last slots of the cable entry port The ends of the grommets where the layers are visible should now be facing each other The grommets cable access sl...

Page 6: ...es are lined up properly to the appropriate slot Press the cable clamp by hand to assure for proper seating Tighten the cable clamp bolts by alternating in a crossing pattern to lower the cable gradua...

Page 7: ...Use tabbing shears to slit the cable jacket at the ring cut approximately 1 to 1 1 2 inches Then peel on side up from the cable to create a tab See Figure 7 12 02 Place the terminal end onto the grou...

Page 8: ...bundles from the Express Feeder cables or from Drop Lateral cables can be safely routed into the flexible routing clips molded into the sides of the center section frame It is recommended that loose b...

Page 9: ...flexible routing rings to join up with the Express Feeder bundles 14 09 Determine the amount of slack required and mark all bundles Dress slack back towards the storage area Note If the ribbons are to...

Page 10: ...and CSM clamp to assure these are tight 16 02 Apply lubricant to the gasket surfaces of the C Half sections and tighten firmly the four 4 captive hex head bolts Use a 216 style tool or 3 8 socket and...

Page 11: ...efer to Photo 19 V Band Alignment to Base 18 03 Flash test the closure to 10 psi maximum using air valve at end of dome Do not over pressurize 18 04 After pressurizing closure to 10 psi check for leak...