7-4
7.8 SHUTTING THE BOILER DOWN FOR
AN EXTENDED PERIOD OF TIME
7.7 CONDENSATE DRAIN TRAP
The Benchmark 2.0LN Boiler contains a
condensate trap as shown in Figure 2-5. The
trap is located external to the unit and attached
to the drain pipe from the exhaust manifold. This
traps should be inspected and, if necessary,
cleaned to ensure proper operation. To inspect
and clean the trap, proceed as follows:
If the boiler is to be taken out of service for an
extended period of time (one year or more), the
following instructions must be followed.
1. Set
ON/OFF
switch on the front panel to the
OFF
position to shut down the boiler’s
operating controls.
2. Disconnect AC power from the unit.
1. Disconnect the external condensate trap by
loosening the hose clamps between the trap
and the connecting manifold drain pipe.
3. Close the water supply and return valves to
isolate boiler.
2. Remove the connections on the inlet and
outlet sides of the condensate trap shown in
Figure 7-4.
4. Close external gas supply valve.
5. Open relief valve to vent water pressure.
3. Loosen the four (4) thumbscrews securing
the cover on the condensate trap. Remove
the cover.
7.9 PLACING THE BOILER BACK IN
SERVICE AFTER A PROLONGED
SHUTDOWN
4. Remove the float from the condensate trap.
5. Remove the orifice gasket from the trap.
After a prolonged shutdown (one year or more),
the following procedures must be followed:
6. Thoroughly clean the trap and gasket. Also
inspect the drain piping for blockage. If the
trap cannot be thoroughly cleaned, replace
the trap.
1. Review installation requirements included in
Chapter 2.
7. After the above items have been inspected
and thoroughly cleaned, replace the orifice
gasket and float in the condensate trap and
replace the trap cover.
2. Inspect all piping and connections to the
unit.
3. Inspect exhaust vent, air duct (if applicable).
8. Reassemble all piping and hose connections
to the condensate trap inlet and outlet.
Reconnect trap to connecting manifold drain
pipe.
4. Perform initial startup per Chapter 4.
5. Perform safety device testing and the
scheduled maintenance procedures per
Chapters 6 and 7 of this manual.
Figure 7-4
External Condensate Trap
Summary of Contents for GF-123
Page 4: ......
Page 8: ......
Page 36: ......
Page 42: ......
Page 68: ......
Page 76: ......
Page 78: ......
Page 84: ......
Page 89: ...APPENDIX F F 5 ...
Page 92: ...APPENDIX F F 8 ...
Page 94: ...APPENDIX F F 10 ...
Page 96: ...APPENDIX F F 12 ...
Page 100: ...APPENDIX G G 4 ...
Page 106: ......
Page 107: ...APPENDIX J BENCHMARK CONTROL PANEL EXPLODED VIEW J 1 ...
Page 108: ...APPENDIX J J 2 P1 P2 P3 P4 P5 P6 BENCHMARK CONTROL PANEL REAR VIEW ...