4.4 Installation of roof cover (TPR-H, TPR-V, TPR-CH, TPR-CV)
•
In the event that roof covers are supplied apart to be mounted later than the unit and/or its external sections
CCS/CDX, it is always possible to install them on the existing unit/sections.
•
For external sections CCS/CDX, both horizontal and vertical version, it is supplied a roof cover which, before
coupling unit and section according to the instructions of next 4.5, shall be interchanged with the unit roof element
placed on the coupling side (
fig. 9a
).
•
For mounting roof cover elements, preventively unscrew the M6 screws by a 5 mm Allen key (
A in fig. 9b
); further,
on vertical unit, the upper bracket (
B
) shall be removed.
•
As first, place the intermediate roof cover plate, fix it by screwing the same M6 screws, preventively provided with
the special rubber washers supplied together with the roof covers.
•
The jointing side of each end side roof plates shall be first hooked to the intermediate plate vertical protrusions
by an about 45° rotation, then placed upon the upper panels and finally fixed by M6 screws with rubber washer.
•
Complete the installation by sealing the connection lines between element and element.