Installation Instructions
1. Requirements of the Installer
All installation work for this immersion heater kit must be carried out by an individual with the relevant
qualifications and experiences to work with electrical systems and who is registered with an electrical regulatory
body such as NICEIC, and should be compliant to:
• BS 7671:2008 IEE Wiring Regulations 17th Edition.
• BS EN 806 all parts.
• BS EN 60335-2-74, IEC 60335-2-74.
• Building Regulation Part G.
• Building Standards (Scotland) Regulations.
• Water Regulations.
• Health and Safety and Work Act 1974.
• Local Byelaws.
And any complementing or superseding documentation.
Adveco Limited accept no responsibility for failure to comply with the above or with safe working practices.
2. Location
For GSM module responsiveness, it is recommended that the control panel should be sited in an above ground
area with good signal reception . Basement installations may require a remote antenna (not included).
The control panel should be mounted at an accessible height on a wall adjacent to the water heater. The wall
should be strong enough to hold the panel and constructed of a suitable material to accommodate the panel
fixings. Should the control panel be installed away from the water heater, additional isolators must be included
near the heater and its components.
Cable connections for all panels enter through the floor of the enclosure and require 100mm of exterior
clearance. All panel dimensions are included in the technical details on pages 7-9
and should be consulted prior
to installation.
The EB0025 features a removable front panel and is suited for installation within cupboards or tight spaces. A
minimum frontal clearance of 300mm is recommended for access.
The EB0028 and EB0030 models feature a hinged front panel. A frontal clearance of no less than 500mm must
be present in order to open the panel door.
5
EB0025-EB0028-EB0030 Control Panel -
Installation and maintenance manual