6
When installing the SR-60 into a rack, the selected location should meet environmental standards as
described below.
Rack Space and Airflow Considerations
To allow for adequate airflow, technicians should observe the following space and airflow requirements
when deciding where to install a rack.
• Leave a minimum clearance of 36in (91.4cm) in front of the rack.
• Leave a minimum clearance of 20in (50.8cm) behind the rack
.
Temperature Considerations
Your SR-60 is designed to operate at room temperature with its self-contained cooling.
Power Considerations
When properly configured and installed the SR-60 can draw up to 2kW depending on the number, load,
and version of the BioDigitalPC
®
s used.
To prevent improper cooling of equipment, do not block the fans.
Section 2.1 - Preparing For Your SR-60
If using the dual feed redundant power solution (See Section 2.6.2), each power source must be
capable of supporting a maximum draw of 2kW.
Section 2 - SR-60 Preparation