08. Unit Lifting Procedure
WARNING
WH&S regulations must be observed and will take precedence during lifting process.
Crane Lifting Method
Note:
Crane lifting method is recommended for high rise lifting.
Fig. 1
Connect the loop ends
of slings into shackle
Provide rubber pads
to prevent damage
to the unit
RUBBER
PADS
LIFTING POINT
Lifting point is located at each corner of
the unit (4 Total). Size:
Ø17.5 mm
EQUIPMENT REQUIRED FOR CRANE LIFTING:
•
1 x Shackle
•
2 x Nylon Slings
•
Spreader Bar
NOTE