Page 18 Roof Window
Install the glass on top of the sidewall and slide it upward between the roof profiles until it does not rest on the sidewall anymore. Pull the glass downward in the provided
slot. Press the crossbeam until it closely fits the underlying glass and assemble it definitively with the special assembly bolts. Put the rubbers in place on the two roof
profiles, in the same way as you did for the rest of the roof.
Also put the rubber on the crossbeam, cut off the rubber diagonally so that it closely fits.
Press a piece of rubber in the round hole of the ridge to avoid the roof window from sliding.
To open the roof window, slide the round bar on the curl in the roof window and on the bolt in the crossbeam. If the roof window is not open, the round bar is put on the
support.
Page 19 Water Drainage
Install all parts with silicone to seal and to lock.
Page 20 Window-Raiser: OPTIONAL
This is an option.
Make sure that the hole in the cylinder axis corresponds to the first hole in the tube. Push the smallest pin with its straight rod through the holes. Make sure that the pin
sticks through the tube. Turn the cylinder completely in the round nut.
First disassemble the roof window; then, disassemble the crossbeam. Slide 2 stop bolts in the bolt slot of the crossbeam. Reinstall the crossbeam. Make sure that the
crossbeam is pressed completely against the glass. Then reinstall the rubber on the crossbeam and have it fit closely to the side that is cut off diagonally.
The numbers of the detailed views indicate the assembly order. Tighten the assembly definitively. Install the base plate firmly on the crossbeam with the two pre-mounted
bolts. Reinstall the roof window in its place and centre it. Clamp the window-raiser base plate on the roof window tongue, using 2 bolts and a stainless steel plate. Turning
the cylinder determines the opening distance of the roof window at a specific temperature.
Page 21 Anchors
Put the greenhouse level again accounting for the desired slope (stimulate water drainage). Support the entire greenhouse with ground until it is completely closed. For the
anchors, dig a hole at the inside of the greenhouse, in each of the corners. Install the anchors with the stop bolts and fill the holes with concrete.
Page 22 reinforcements
Overview for placement of the gutter and ridge supports and middle anchors.
Summary of Contents for R410
Page 2: ......
Page 33: ...GEVEL PIGNON GABLE GIEBEL 2 B B B B B B B B B B 1 2 3 4 5 6 7 8 1 2 4 6 3 5 7 8 ...
Page 36: ...KADER CADRE FRAME RAHMEN 5 2 1a 1b 2 1a 1b 1a 1b 1a 1b 1a 1b 2 2 2 ...
Page 42: ...VOORBEREIDING PRÉPARATION PREPARATION VORBEREITING 10 1 2 A B 3 3 A B 2 2 2 2 2 3 3 2 ...
Page 47: ...DEUR PORTE DOOR TÜR 15 2 3 1 4 2 3 1 4 ...
Page 49: ...DEUR PORTE DOOR TÜR 17 1 2 b a 1 2x 2 ...
Page 56: ...AFDEKPLAATJES PLAQUETTES DE FINITION COVER PLATES ABDECKPLATTEN 23 ...
Page 57: ...RAAMOPENER OUVRE FENÊTRE WINDOW OPENER FENSTERÖFFNER 24 3 2 1 2 1 3 OPTIE OPTION ...
Page 58: ...RAAMOPENER OUVRE FENÊTRE WINDOW OPENER FENSTERÖFFNER 25 6 7 1 2 3 4 5 8 a b 2 4 1 6 3 7 5 8 ...
Page 60: ...DBER05062019 ACD R410 ...