12  

 

 

1. Centre Truss

Secure centre truss to edge 
beams.
Measure in 2960 mm from one 
end of the edge beam to mark 
the centreline of the truss.
Secure three 

MPB

 to each side 

as shown with 6 screws. Truss 
must sit 80 mm up from the 
underside of the edge beam.
Repeat for other beam then 
safely lift truss into position and 
secure with hex head tek screws.
NOTE: You will have to remove 
wafer head tek screws where 
they interfere with the 

MPB

s.

2. Post Angle Braces

•  Use two 

ZACO232

 angle 

braces to sandwich post 
and truss. Fasten with 6 tek 
screws per end. Make sure to 
use wafer head tek screws to 
outside of truss where sheet 
will cover later.

•  Position ZACO122 inside face 

of edge beam to outside face 
of post. Fasten with 3 hex 
head tek screws per end.

NOTE: Ensure all posts are 
vertical and make sure all braces 
are fastened at 45 degrees.

3. Purlins

Place all four purlins on ‘uphill’ 
side of brackets and secure 
with 4 hex head tek screws per 
bracket.

ZACO232

ZACO122

Edge beam

80

CL

Edge beam

FRAME ASSEMBLY

End truss

Purlin

Purlin bracket

Refer to the engineering 

drawings for further detail 

such as screw fixing details.

Summary of Contents for GCPSN2

Page 1: ...bscosheds com au DOWNLOAD OUR APP FOR ASSEMBLY VIDEOS PLEASE LEAVE A REVIEW Tell us about your experience Visit www abscosheds com au review 6445 mm 3425 mm Concrete slab footings detailed in engineer...

Page 2: ...mponents may be packed inside others almost hidden Carefully examine inside each component to ensure that you have located every item If a discrepancy is found contact Absco Industries immediately Don...

Page 3: ...IPTION PART CHK 6 TRUSS OUTER INFILL 450 mm C0450 6 TRUSS OUTER INFILL 600 mm C0600 8 ROOF PURLIN 2960 mm C2960 4 PURLIN JOINER 200 mm C0200 QTY DESCRIPTION PART CHK 4 OUTER EDGE BEAM 1585 mm ZACO 117...

Page 4: ...BRACKET RWG 06 4 GUTTER END STOP TR25 6 TRUSS SIDE JOINER PLATE 70 x 450 mm ZACO 181 14 MULTIPURPOSE BRACKET MPB BKT 17 16 COLUMN BASE BRACKET 12 mm HOLE BKT 03 3 FLY BRACE 40 x 40 x 450 mm ZACO 134...

Page 5: ...gs as noted in A Pour a perfectly level slab to the dimensions specified in the engineering drawings Alternatively you may prefer the slab to finish flush with the outside of the footings The slab wil...

Page 6: ...frame section to be spread over the sides of another frame section boxed frame section or H section Absco sheds frame sections are designed to nest into one another to create boxed frame sections Boxe...

Page 7: ...height at the centre and make sure it is perpendicular to the bottom chord 3 Fasten all frame pieces with two wafer head tek screws per tab Use six screws per side at the end where the top chord fits...

Page 8: ...and fix with 4 more screws Repeat these steps until you have three completed trusses 1 Layout the framing pieces as shown 2 Box the C0200 halfway into one end of a C2960 and fasten with 2 wafer head t...

Page 9: ...oceed to fastening Fasten all with tek screws at 300 centres TIP The top side of the beam needs wafer head teks The underside of the beam can be hex head tek screws 3 Remove all screws for the two out...

Page 10: ...our faces of the column 3 Place a BKT03 and fasten with a pair of M10 x 20mm bolts nuts and washers Poke the bolt through from the inside of the post and use a nut and washer on the outside Turn over...

Page 11: ...ting or collapse Assemblies are too heavy for 1 person to lift unaided Please refer to engineering drawings that specify concrete footings slab and post distances Safely lift a truss and place on top...

Page 12: ...where they interfere with the MPBs 2 Post Angle Braces Use two ZACO232 angle braces to sandwich post and truss Fasten with 6 tek screws per end Make sure to use wafer head tek screws to outside of tr...

Page 13: ...to be bent to suit and fit to the underside of truss with two hex head tek screws Fly brace Purlin Truss underside 40 45 degrees FRAME ASSEMBLY ZACO133 ZACO133 ZACO134 5 Roof strapping Lay roof strap...

Page 14: ...ill overhang the edge beam by min 30mm for the gutters 2 Use Hex head tek screw with neoprene washer FAST035 at every pan to top purlin and edge beam Use one Hex head tek screw with neoprene washer at...

Page 15: ...side of a gable end Repeat the last steps with the angle going the other way to make the two left sheets 3 Repeat steps until you have enough pieces to sheet the front and rear of the carport 8 sheets...

Page 16: ...he edge beam at either end and spaced equally along the length You may adjust bracket height to allow for a slight fall to the downpipe position 8 Fit gutter onto all brackets at once Push top of brac...

Page 17: ......

Page 18: ......

Page 19: ...ws garden tools etc Storage items that might be adversely affected by any of the above conditions may require additional protection such as being sealed or covered by plastic sheets and or stacked abo...

Page 20: ...s of claiming warranty To make a claim under the warranty within the warranty period you will need to contact the manufacturer directly by phone or email Contact Number 1800 029 701 Contact Email admi...

Page 21: ...itions such as extreme heat or cold The product should only be used for storing items such as gardening equipment and should not be used for articles that may be prone to damage if they come into cont...

Reviews: