Production Start Up Sheet- American Beer Equipment
Department
Date
Product Being Produced
Raw Material #1
Raw Material #2
Raw Material #3
Can
Component Number
Lid Component Number
Case
Component Number
Finished
Product/SKU Number
Total Number To Be Produced
(cans, bottles, cases, etc.)
Verbal Description of Product
Produced
Process Leader's Name
(please Print)
Lead Operator's Name (please print)
Specific Start Up Check List
Task
Number
Leader
Initials
Operator
Initials
Pre-Run/Set-Up Task Description with Specific Detail Relative to Task,
Measurements, Settings, outcomes critical to quality, safety, etc.
1
Ensure seamer lock nut for roller operation # 1 and roller operation #2 is
tight - (Spare Parts, Figure 1, #4)
2
Ensure operation #1 and operation #2 seamer set screw, on canning line # 1
and canning line #2, is tight - (Spare Parts, Figure 1, #3 )
3
Ensure seaming chuck set, including screw, is tight (Spare Parts, Figure 2,
#11) and visually inspect the chuck for tightness (if it is tight, there will be
no gap between the chuck and upper adapter)
4
Ensure the complete seamer cylinder, and lower bearing assembly, bolts are
tight (130 Nm). (Spare Parts, Figure 2, #13)
5
Ensure lower seamer puck is not loose or wobbly (Spare Parts, Figure 2, #16)
6
Ensure flow control jam nuts are not loose. (Spare Parts, Figure 2, #12 and
#15)
7
Warm water wash any cylinder that has been exposed to beer. Special
attention must be directed to the shuttle cylinder that moves cans into the
seamers. (Spare Parts, Figure 3, # 18)
8
Lubricate (food grade lubricant) all cylinders following warm water wash.
9
Check for smooth cylinder operation (shuttle into steamer, filler nozzle, lid
taps, seaming cylinders, etc.) and seaming rollers. If not traveling smoothly,
repeated warm water wash and lubrication process.
10
Following warm water wash/lubrication, observe cylinder speed and adjust
flow control. Travel rate of cylinder should be controlled and fast enough to
Summary of Contents for CraftCan 15
Page 38: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 37 ...
Page 40: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 39 ...
Page 42: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 41 ...
Page 44: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 43 ...
Page 47: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 46 Figure 30 Timing Setup ...
Page 49: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 48 Figure 32 Diagnostics Screen ...
Page 50: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 49 Figure 33 Can Count ...
Page 53: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 52 Figure3 5 Setting Menu ...
Page 59: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 58 ...
Page 60: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 59 ...
Page 61: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 60 ...
Page 62: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 61 ...
Page 63: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 62 ...
Page 64: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 63 ...
Page 65: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 64 ...
Page 66: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 65 ...
Page 67: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 66 ...
Page 68: ...American Beer Equipment 2001 SW 6th St Lincoln NE 68522 67 ...