WBPEEUI210509A1
PR16 - 1
PR16
Checking Connections
Purpose/Scope
This procedure explains how to check connections.
Parts
None.
Tools
Individual tools cannot be listed due to the numerous connec-
tions involved.
Safety Considerations
Procedure
Check all signal wiring, power, and ground connections within
the cabinet to verify their integrity. When checking connec-
tions, always turn a screw, nut or other fastening device in the
direction to tighten only. If the connection is loose, it will be
tightened. If the connection is tight, the tightening action will
verify that it is secure. There must not be any motion to loosen
the connection.
□
1. Be sure power is removed at the source before starting this
procedure.
□
2. Check and verify that all line, neutral, and grounding con-
ductor connections on the PEP are secure and within the
torque values listed in Table
PR16-1
.
□
3. Check and verify that all other power connections within
the cabinet, including connections to the power chassis are
secure and within the torque values listed in Table
PR16-1
.
□
4. Check and verify that all field wiring connections to the
modules are secure.
1 hr
WARNING
1. Disconnect power before attempting these procedures. Fail-
ure to do so could result in severe or fatal shock, or equipment
damage.
W1
Summary of Contents for Symphony Harmony Series
Page 1: ...Instruction Harmony Series Modular Power System III...
Page 9: ...WBPEEUI210509A1...
Page 17: ...WBPEEUI210509A1...
Page 25: ...WBPEEUI210509A1...
Page 33: ...WBPEEUI210509A1...
Page 43: ...WBPEEUI210509A0...
Page 57: ...WBPEEUI210509A0...
Page 59: ...WBPEEUI210509A0...
Page 65: ...WBPEEUI210509A0...
Page 69: ...WBPEEUI210509A0...
Page 79: ...WBPEEUI210509A0...
Page 101: ...WBPEEUI210509A1...