9.10
Station communication
SEMOD53595-1 v1
9.10.1
Multiple command and transmit MULTICMDRCV /
MULTICMDSND
SEMOD172432-5 v3
The multiple command and transmit function (MULTICMDRCV / MULTICMDSND) is only
applicable for horizontal communication.
Test of the multiple command function block and multiple transmit is recommended to be
performed in a system, that is, either in a complete delivery system as an acceptance test
(FAT/SAT) or as parts of that system, because the command function blocks are connected in
a delivery-specific way between bays and the station level and transmit.
Command and transmit function blocks included in the operation of different built-in
functions must be tested at the same time as their corresponding functions.
9.11
Basic IED functions
SEMOD52026-1 v1
9.11.1
Parameter setting group handling SETGRPS
M11369-2 v4
Prepare the IED for verification of settings as outlined in section
in this
chapter.
9.11.1.1
Verifying the settings
M11369-4 v5
1.
Check the configuration of binary inputs that control the selection of the active setting
group.
2.
Browse to the ActiveGroup menu to achieve information about the active setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test/Function
status/Setting groups/ActiveGroup
The ActiveGroup menu is located on the PCM600 underMain menu/Test/Function
status/Setting groups/ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary input of the IED and
observe the information presented on the local HMI.
The displayed information must always correspond to the activated input.
4.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting groups
are described in the corresponding PCM600 documents and instructions for the
operators within the SCS are included in the SCS documentation.
9.11.1.2
Completing the test
M11369-39 v4
continue to test another function or end the test by changing the
TESTMODE setting to Off.
Restore connections and settings to their original values, if they were changed for testing
purposes.
9.12
Exit test mode
SEMOD53244-3 v6
The following procedure is used to return to normal operation.
1MRK 505 385-UEN C
Section 9
Testing functionality by secondary injection
Breaker protection REQ650
99