3 - Mounting and wiring
P
arallel mode bottom switch wiring box and -S version with
AFD
In the inverter box
, parallel the two MPPT inputs of terminal [–IN1 and –IN2] and [+IN1 and
+IN2] as shown below, using the two #10 AWG jumper wires provided (one black and one red
cable) to connect the input.
A
C grid connection
AC output overcurrent protection is not provided with the inverter; it is the responsibility of the end
user to provide overcurrent protection for the AC output circuit.
The default AC grid connection, 240VRMS/3W/Split-Phase, requires the neutral terminal to be
connected to the grid neutral conductor for proper operation.
Before connecting the inverter to the grid, the grid type must be selected if it differs from the default
240V-SPLIT PHASE setting. See Operations, section 4 > Set Vgrid, for instructions to change the
default.
-ju
m
per
+
ju
mpe
r
Summary of Contents for PVI-3.0-TL-OUTD-S-US
Page 1: ...ABB solar inverters Product manual PVI 3 0 3 6 3 8 4 2 TL OUTD S US A 3 0 to 4 2 kW ...
Page 16: ... 16 3005CC2 2 Installation location ...
Page 32: ... 32 3007CC3 3 Mounting and wiring ...
Page 62: ... 62 C011C5 5 Troubleshooting ...
Page 66: ... 66 C012C6 6 Maintenance ...
Page 72: ... 72 C013C7 7 Appendix Output power with one DC section operating ...