Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
69
2.
Remove the nuts and washers.
G006964
3.
Remove the winding cables from the fixed bottom
contact.
G007610
4.
Lift the bushing from the transformer.
CAUTION!
Do not damage the stud bolts, there is
a risk of metal falling into the
transformer.
G007251