Installation and commissioning guide
1ZSC000563-AAF EN, REV. 4, 2021-06-23
51
6.
Apply Molykote Multilub to the M10 bolts (6).
G004690
7.
Install the M10 bolts (6) and plain washers (7).
8.
Tighten the M10 bolts (6) in a crosswise
sequence.
CAUTION!
Make sure that the outer terminal
moves straight down. Turn each bolt a
little, and then the next bolt, until all
bolts can be tightened to the correct
torque.
G003053
Torque
40 ±4 Nm
9.
Tighten the M8 bolts (24) in a crosswise
sequence.
G004684
Torque
20 ±2 Nm
10.
Install the external connection. Refer to the documentation from the supplier of the external
connection.
End of instruction
Summary of Contents for GOE 2600
Page 12: ...12 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 18: ...18 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 78: ...78 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...
Page 82: ...82 Installation and commissioning guide 1ZSC000563 AAF EN REV 4 2021 06 23 ...