Installation and commissioning guide
2750 515-1 EN, REV. 14, 2020-06-26
9.
Hold the pull-through cord (12) in tension, while
lowering the bushing onto the transformer.
CAUTION!
Do not damage the stud bolts on the
transformer. There is a risk of metal
falling into the transformer.
CAUTION!
Make sure that the draw lead is
entering the bushing correctly. Monitor
the draw lead through the inspection
openings on the transformer.
NOTE!
Plastic sleeves put on two or three of
the stud bolts will help to guide the
flange, and will prevent damage to the
stud bolts.
G006853
10.
If necessary, adjust the length of the inner
terminal:
1.
Lift the bushing from the transfomer and
lower the inner terminal with the pull-through
cord.
2.
Remove the screws (34) with spring washers
(34) .
3.
Move the lower part (14).
4.
Apply Molykote Multilub to the threads of the
screws (34) and install the screws (34) with
spring washers. Both screws should be used.
CAUTION!
Make sure that there is no tenison in
the straded cable, or too much slack.
NOTE!
The lower part of the inner terminal can
be moved in steps of 30 mm.
G004514
Torque
37.5 Nm
11.
If the bushing is installed in a non vertical position:
•
For GOE 250 to 950: the sight glasses (25)
must be perpendicular to the angle of the
bushing.
•
For GOE 1050 to 2600: the oil-guage (26)
must point down.