ARC GUARD SYSTEM™ – CSU-2LV/2MV INSTALLATION AND MAINTENANCE GUIDE
27
4.3
Setting the system
This chapter describes the eight mandatory steps to
succeed in setting the system. All settings are done in the
Human Machine Interface, HMI. Settings are made only
with the power on.
4.3.1
Start-Up Sequence
Installation of the CSU-2 requires configuration of
the system and its modules to work. This start-up is
mandatory. The same start-up occurs when operating
the CSU-2 for the first time and after a factory reset.
The Human Machine Interface (HMI) automatically goes
through the different configuration steps.
For more information, see section 5.2.
To do the Start-Up sequence follow the steps below, at
all times the home button can be pressed to restart the
start-up sequence:
1.
Language
2.
Set date
3.
Set time
4.
Inputs (Number of Current Sensors)
5.
Correction factors (Only CSU-2MV)
6.
Warning (Current Warning threshold)
7.
Over Current (Over Current threshold)
8.
Automatic reset
9.
Daisy chain
INFORMATION
The system will not require the Start-Up
sequence in the event of a power loss.
04
Summary of Contents for CSU-2LV
Page 2: ......
Page 4: ......
Page 6: ......
Page 8: ......
Page 12: ......
Page 17: ...ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 17 03 ...
Page 18: ......
Page 29: ...ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 29 04 ...
Page 30: ......
Page 38: ......
Page 66: ...66 ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 06 ...
Page 69: ...ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 69 07 ...
Page 70: ......
Page 75: ...ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 75 08 ...
Page 76: ......
Page 83: ...ABB ARC GUARD SYSTEM CSU 2LV 2MV INSTALLATION AND MAINTENANCE GUIDE 83 09 ...