Standard Commissioning Process 27
Protection relays
ACS580MV with integrated transformer
The protection relays in the feeding switchgear for the converter’s transformer must be
commissioned and tested as per the manufacturer’s documentation.
The settings for the protection relay are defined by the protection or system engineer. The
commissioning engineer should only verify these values.
Relay test protocols must be available on site before the drive is energized.
A protection curve can be programmed into the relay. The protection curve defines how
long a current of a certain magnitude is allowed to flow until the relay opens the MCB.
There are three types of protection modes:
•
Instantaneous
•
Short delay
•
Time over current protection
Transformer protection modes
The recommend protection functions and setting values:
NOTICE
The below mentioned settings are just informative for the commissioning
engineer, in which range the protection settings should be made. The customer is fully
responsible for the protection settings.
Protection functions
Setting value
Immediate overcurrent trip level
10 times the rated current of the
ACS580MV
Short time delay overcurrent trip
level
2 times the cable rated current with
500ms delay
Long time delay protection pickup
level
1.3 times the rated input current of the
ACS580MV
Summary of Contents for ACS580MV
Page 1: ... ABB INDUSTRIAL DRIVES ACS580MV Commissioning Manual 200kW to 6300 kW 3 3kV to 11 kV ...
Page 4: ......
Page 8: ...8 ...
Page 43: ...Standard Commissioning Process 43 Press the button Load SW and wait till update is finished ...
Page 60: ...60 Standard Commissioning Process Complete the installation press Finish ...
Page 83: ...Standard Commissioning Process 83 ...
Page 96: ...96 Standard Commissioning Process ...
Page 121: ...Option 121 IO signals ...
Page 122: ...122 Option Panel control interface System fault ...
Page 140: ...140 Option ...
Page 148: ...148 Preventive Maintenance ...