![AAQ SXJS4019A Installation Manual & Operation Instructions Download Page 24](http://html1.mh-extra.com/html/aaq/sxjs4019a/sxjs4019a_installation-manual-and-operation-instructions_449263024.webp)
23
column top cover, and the steel rope needs to be selected to pass through the
corresponding hole.
3.7 Vertical adjustment of column required
:
Use a spirit level to adjust the verticality of the column. The angle of the column
should be less than 1 ° (in the direction indicated by the arrow in the figure below) so
that the lift can offset the elastic deformation that occurs when the load is lifted. 16
pieces of M16 * 120 expansion bolts are fixed, and the tightening torque of the nuts of
the expansion bolts is about 80N.M. If the level of the ground causes the vertical
requirements of the column to be unsatisfactory, you need to use a U-shaped
adjustment pad to insert the expansion bolt at the base of the column for adjustment
(the position indicated by the arrow at the bottom of the column in the figure below).
See the figure below:
U shape Pad
Install the other three columns in the same way; so far, the installation of the lift body
is basically completed.
IV
、
Electrical and oil pipe installation instructions
1 Electrical parts connection
:
1.1 Firstly install the electric control box on the main column and connect it with 4
pieces of M6*25 hex screws
;
Pneumatic unlocking solenoid valve is fixed on the
column with 2 pieces of M6*10 hexagon socket screws
;
the pump station is installed
on the pump station base with 4 pieces of M8*30 flange bolts and screws nut.As
illustrated in below picture:
Summary of Contents for SXJS4019A
Page 9: ...8 Top view of steel rope general arrangement ...
Page 43: ...10 2 2 Warning mark ...
Page 55: ...22 ...
Page 56: ...23 Chapter 7 Hydraulic System 7 1 Hydraulic pressure principle drawing ...
Page 60: ...29 ...
Page 61: ...30 ...
Page 62: ...31 ...
Page 63: ...32 ...
Page 64: ...33 ...
Page 65: ...34 ...