5
Installation, Operation and Parts Manual
AutoLift AL-6254
3.1
Preparations before installation
3.1.1 Tools and equipments needed
Appropriate lifting equipment
Anti‐abrasion 32 grade hydraulic oil.
Rotary Hammer Drill with 18mm masonary drill bit.
Chalk and tape measure, magnetic level.
Sockets and open wrenches, a set of inside hex wrenches, star and straight screw drivers.
Hammer, 4pounds, sharp nose pliers, Ф14 Ф17,Ф18,Ф22 socket spanners
。
3.1.2
List for parts checking ‐‐‐Annex 1
(
Packing list
)
Unfold the package and check if any parts missed as per Annex 1. Please contact us in case any parts are missing, but do note
if you do not contact us and insist installing despite the lack of some parts, Advance AutoQuip as well as our dealers will not bear any
responsibility for this and will charge for any parts subsequently demanded by the buyer.
3.1.3
Ground conditions
The hoist should be fixed on a flat, level and solid concrete surface with its strength more than 3000psi, tolerance of flatness
less than 5mm and minimum thickness of 150mm. In addition, newly laid concrete ground must undergo more than 28 days
cure time.
3.2
Precautions for installation
3.2.1
Make sure the two posts stand parallel. NOTE: once both posts are firmly bolted to the concrete floor, use shims to lean the columns
outwards by 25mm to allow for deflection.
3.2.2
Joints of oil hose and steel cable must be firmly connected in order to avoid looseness of steel cable and leakage of oil.
3.2.3
All bolts should be firmly screwed up.
3.2.4
Do not place any vehicle on the hoist for trial running.
3.3
Installation
Step 1: Remove the packaging, take out the carton for accessories and cover plate.
Step 2: Firstly, put something supporting between the two posts or suspend one of the posts by a crane and then remove the bolts
from the packing frame.
Attention
:
Please pay special attention not to let the post fall down for it may cause casualty or bring damages to the accessories
fixed in the post.
Step 3: When the first post has been removed, place some packing under the second post and then remove the bolts from the
packing frame.
Step 4: Fix the standing position for the two posts. (See Annex 3, floor plan) .