Step 13: Locking Mechanism.
Do refer to the operation instructions in advance and keep in mind that
NO
vehicle is to be placed on the hoist
during trial run.
1. Route lock cable and conduit down the inside of the motor post down to bottom channel plate, then over to the inside of the next column,
then up to the lock assembly.
2. Loop the pull cable over the pull handle latch bolt then lock off with barrel union. Apply tension to lock cable on opposite post lock latch
bracket then lock off with barrel union.
3. Check mechanical locks for correct engagement by releasing the lock during the running process. Adjust by tightening the wire cable
on the lock latch. NOTE: Hoist must be rested on locks during adjustments.
Step 14: Connect Power and do a trial run.
1. Assure all the connections are in good condition and connect the power supply.
Step 15: Fix feet protection fenders, door‐opening protections, tool trays and lock covers.
3.4
Items to be checked after installation.
S/N
Check items
YES
NO
1
Are the posts vertical to the floor?
2
Are the two posts paralleled?
3
Is the oil hose well connected?
4
Is the steel cable well connected?
5
Are all lifting arms well fixed?
6
Are electrical connections right?
7
Are the rest joints firmly screwed?
8
Are all items need lubricating added with grease?