F1 Series Startup Form
Job Name:_______________________________________________
Date:______________
Address:______________________________________________________________________
______________________________________________________________________________
Model Number:_________________________________________________________________
Serial Number:_____________________________________________ Tag:_______________
Startup Contractor:______________________________________________________________
Address:______________________________________________________________________
_______________________________________________________
Phone:______________
Pre Startup Checklist
Installing contractor should verify the following items.
1.
Is there any visible shipping damage?
Yes No
2.
Is the unit level?
Yes No
3.
Are the unit clearances adequate for service and operation?
Yes No
4.
Do all access doors open freely and are the handles operational?
Yes No
5.
Have all shipping braces been removed?
Yes No
6.
Have all electrical connections been tested for tightness?
Yes No
7.
Does the electrical service correspond to the unit nameplate?
Yes No
8.
On 208/230V units, has transformer tap been checked?
Yes No
9.
Has overcurrent protection been installed to match the unit nameplate
requirement?
Yes No
10.
Have all set screws on the fans been tightened?
Yes No
11.
Do all fans rotate freely?
Yes No
12.
Does the field water piping to the unit appear to be correct per design
parameters?
Yes No
13.
Is all copper tubing isolated so that it does not rub?
Yes No
14.
Are air filters installed with proper orientation?
Yes No
15.
Have condensate drain and p-trap been connected?
Yes No
Ambient Temperature
Ambient Dry Bulb Temperature ________°F
Ambient Wet Bulb Temperature ________°F
Summary of Contents for F1-024
Page 31: ...31 ...
Page 36: ...36 Figure 8 Heat Pump Piping Diagram with Indoor Unit above Outdoor Unit ...
Page 37: ...37 Figure 9 Heat Pump Piping Diagram with Outdoor Unit above Indoor Unit ...
Page 40: ...40 Thermostat Installation and Wiring Figure 12 2 Stage Cooling with Electric Heat ...
Page 41: ...41 Figure 13 2 Stage Cooling with Heat Pump and Electric Heat ...
Page 42: ...42 Figure 14 2 Stage Cooling and Electric Heat with Hot Gas Reheat and Humidistat ...
Page 43: ...43 Figure 15 Main Control Board for Units Equipped with Modulating Hot Gas Reheat ...
Page 45: ...45 Figure 17 5kW Electric Heat ...
Page 46: ...46 Figure 18 10 kW Electric Heat ...
Page 47: ...47 Figure 19 15 kW Electric Heat ...
Page 48: ...48 Figure 20 20 kW Electric Heat ...
Page 49: ...49 Figure 21 25 kW Electric Heat ...
Page 55: ...55 ...