Single Phase Installation (X7110 & X7111 Only)

All single phase models require start capacitor, run capacitor and relay in the circuit to start and operate properly. These components can be 

purchased separately or prewired in a Zoeller control panel. For components purchased separately use the diagram for installation and hookup.
Single phase models are nonautomatic. To operate automatically a control panel  must be added to the power circuit. Follow the instructions 

provided with the panel.

WIRING DIAGRAM

COMPONENT LAYOUT

2

1

5

WHITE

PUMP

START

MAIN

BLACK

L2

WHITE

BLACK

RUN CAPACITOR

RED

START CAPACITOR

L1

T2

T1

3

2

1

GREEN

230 VAC 1ø

(SEE CHART)

(SEE CHART)

R

RELAY

START

MODELS

7110 / 7111

START CAP.

270-324UF 250V

RUN CAP.

50UF 370V

ZEPA0537C

5

2

1

WHITE

RED

PUMP

MAIN

START

L1

L2

BLACK

WHITE

230 VAC 1Ø

FROM CONTACTOR

START

BLACK

START

RELAY

CAPACITOR

RUN CAPACITOR

1

2

3

GREEN

Three phase pumps are nonautomatic. To operate automatically, a 

control panel with level control is required. Follow the instructions 

provided with the panel to wire the system.

Before installing a pump, check the pump rotation to insure that 

wiring has been connected properly to power source, and that 

the green lead of power cord (See wiring diagram), is connected 

to a valid ground, Momentarily energize the pump, observing the 

directions of kick back due to starting torque. Rotation is correct if 

kick back is in the opposite direction of rotation arrow on the pump 

casing. If rotation is not correct, switching of any two power leads 

other than ground, should provide the proper rotation. 

Refer to the wiring diagram supplied with specific electrical control 

panel for correct electrical cable termination locations.

NOTE 1:

 Sensor cable includes 5 leads; 2 leads for thermal sensor, 2 leads for 

moisture sensor, and a green ground lead. Sensor wire colors are as shown.

330K OHMS RESISTANCE

SEAL FAILURE PROBES

3 PHASE MOTOR

SEAL FAILURE MOISTURE SENSOR

LEADS MUST BE CONNECTED TO 

INDUCTION CIRCUIT IN THE CONTROL

PANEL.

THERMAL SENSOR

T1

T2

L1

L2

T3

L3

3Ø VAC

BLACK

GREEN

WHITE

SENSOR CABLE

RED

(N/C)

STARTER COIL

POWER CABLE

ORANGE

RECOMMENDED THERMAL SENSOR

CONNECTED IN SERIES WITH

ZEPA0038G

ZEPA0538

Содержание X71 Series

Страница 1: ...1 Limited Warranty 2 Preinstallation Information 3 Electrical Data 3 Typical Sewage Installation 4 Pump Wiring Instructions 5 6 Operation 7 Maintenance 7 Service Checklist 8 Safety Instructions TO AVOID SERIOUS OR FATAL PERSONAL INJURY OR MAJOR PROPERTY DAMAGE READ AND FOLLOW ALL SAFETY INSTRUCTIONS IN THIS MANUAL AND ON THE PUMP THIS MANUAL IS INTENDED TO ASSIST IN THE INSTALLATION AND OPERATION ...

Страница 2: ...ment parts For additional information pertaining to our warranty or if service cannot be obtained locally contact Zoeller Engineered Products 3649 Cane Run Road Louisville Kentucky 40211 1961 Attn Customer Service ZOELLER ENGINEERED PRODUCTS EXPRESSLY DISCLAIMS LIABILITY FOR SPECIAL CONSEQUENTIAL OR INCIDENTAL DAMAGES OR BREACH OR EXPRESSED OR IMPLIED WARRANTY AND ANY IMPLIED WARRANTY OF FITNESS F...

Страница 3: ...in in detail the requirements for the installation and wiring of electrical equipment in hazardous locations 1 Not for use in acidic atmospheres 2 Do not lift carry or hang pump by the electrical cables Damage to the electrical cables can cause shock burns or death 3 Make sure there is a properly grounded connection available All pumps are furnished with provisions for proper grounding to help pro...

Страница 4: ...ble electrical and plumbing codes including but not limitedto NationalElectricalCode local regional and or state plumbing codes etc ZEPA0560 1 Electrical wiring and protection must be in accordance with the National Electrical Code per NEC articles 500 through 503 for installation in Class I Division 1 Group C D Class I Zone 1 Groups IIA IIB locations and any other applicable state and local elect...

Страница 5: ...rcuit in the seal cavity where 2 seal leak probes are housed An indicator light will activate whenever water is present in the cavity Whenever the seal leak light is activated indicating that the lower seal has failed the pump should be removed and serviced in order to avoid damage to the motor 3 The green wire shall be connected to a ground lug in the panel CONTROL PANELS These pumps require a co...

Страница 6: ...a control panel with level control is required Follow the instructions provided with the panel to wire the system Before installing a pump check the pump rotation to insure that wiring has been connected properly to power source and that the green lead of power cord See wiring diagram is connected to a valid ground Momentarily energize the pump observing the directions of kick back due to starting...

Страница 7: ...sired location of each float function Valves Dischargevalvesshouldbeplacedinthefullyopenposition Systems shouldnotbeoperatedforextendedperiodsoftimewiththedischarge valves partially closed due to damaging the valve SHUTDOWN PROCEDURES If a system is shutdown for more than six months the following is recommended Pumps If pit is to remain dry then the pump can remain in the pit With the pumpinthepit...

Страница 8: ...in head and or capacity after a period or use Increase Pipe Friction Clogged line or check valve Abrasive material chemical deteriorated impeller and pump housing If the above check list does not uncover the problem consult the factory Do not attempt to service or otherwise disassemble pump Service Checklist Trouble Shooting Steps Check Voltage At If No Voltage If Voltage No 1 Line terminals in pu...

Отзывы: