Zoeller 7020 Скачать руководство пользователя страница 6

6

© Copyright 2020 Zoeller

®

 Co. All rights reserved.

  1.  Review the drawing in Fig. 4 on page 5 and the actual system to 

become familiar with the components in the packaged grinder pump 

system.  Review where the unit will be installed.  Determine where 

the power feed, inlet pipe, and discharge pipe will be located.

  2.  Remove the unit from packing.  Prepackaged outdoor systems are 

preassembled at the Zoeller Company and require a minimum of 

field assembly work.  Float switches are set and tethered for proper 

operation from the Factory.  The alarm switch should be located 2” 

above the pump “on” level.

  3.  Float switches are tied in place for shipping purposes on all model 

prepackaged systems.  Cut the cable tie around each float switch 

bulb or the unit will not operate properly.  Verify that where the float 

switches are set will work for your application.  

Verifying that the 

float switches are set properly and will not hang up inside the basin is 

the responsibility of the installing contractor. 

  4.  Dig a hole for the basin.  The hole should be at least 24” larger in 

diameter than the basin diameter to provide 12” of backfill all around 

and deep enough to provide either 12” of compacted backfill or 6” 

when a concrete pad is required.  Ensure the removable cover extends 

above the finished grade line and the grade slopes away from the unit.  

Backfill and subbase should be 1/8” –3/4” pea gravel or 1/8” –1/2” 

crushed stone.  (Reference basin installation instructions included 

with unit)

 

5.

 

Note:  Care must be taken when excavating in order to avoid underground 

utilities and disturbance of existing structure foundations.  The hole should 

be located at least ten feet from adjacent structures.  Additional distance 

may be required to sufficiently locate the basin outside of the loading area 

of the adjacent structures.

  6.  The location of the inlet fitting is determined by the depth of the inlet 

pipe.  The inlet fitting must be used with 4” pipe.  It is best to install the 

inlet on the side of the basin opposite the float switches.  To install, use 

a 5” hole saw to drill into the side of the basin at the correct elevation.    

Center the hub inner diameter with the hole in the basin.  Attach the 

hub to the side of the basin using the sealant and hardware provided.

  7.  The bottom of the excavation can now be back filled and compacted.  

Set basin in hole and connect the 4” inlet pipe to the inlet hub.  

  8.  The discharge piping is connected to the 1-1/4” threaded fitting 

located in the basin sidewall.

  9.  Connect pull rod to Pump assembly.  Connect lift cable to top of pump.  

Lower the pump into basin ensuring the discharge pipe bracket slides 

into the disconnect fitting.

  10.  Pouring a concrete anchor around system can now be completed.   

Basin should be filled with water when pouring concrete to minimize 

movement of the system.  Back fill around basin with specified 

media.  Care should be used to avoid damaging components 

or leaving voids when back filling.  Refer to Basin installation 

reference guide on more specific requirements.

 

11.

 

Note: The progressing cavity grinder basin is a sewage holding tank.  

Vent connection should be installed in accordance with all national, 

state and local plumbing codes.  

 12.  Dig a trench for the electrical conduit.  Trench should be located 

at least 18” deep and follow all applicable NEC codes.  Connect 

electrical wiring to Junction box according to wiring instructions 

included in this manual and wiring diagram in box.  Use the potting 

kit provided with the junction box. Use the included sealant when 

closing junction box.

 13.  If used, a control panel is installed within sight of the system.  

Connect float switches and pump cords according to the “Pump 

Wiring Instructions” found in this manual and located inside the 

panel enclosure.

  14.  Remove any debris from the basin.  Using clean water, check the 

system for proper operation.

 15.  Seal and secure the lid using the proper bolts and sealant when 

using a lid without a formed gasket. 

 16.  Add water to the basin and test the system for leaks and proper 

pump operation.

  17.  Record system start up data for future reference.

OUTDOOR PREPACKAGED SYSTEM INSTALLATION INSTRUCTIONS

This set of instructions is for factory prepackaged outdoor progressing cavity grinder systems only.  If this is a field assembled outdoor 
system you can use these instructions as a guideline.

GENERAL

Zoeller pumps are lubricated and tested at the factory prior to shipment 

and require minimum pre-start-up maintenance.
Maximum operating temperature of pump liquid for grinder pumps must 

not exceed 130 °F (54 °C).
These units are not designed to handle liquids other than sanitary sewage. 

If pump is used to dewater areas with contaminated liquids with heavy 

or abrasive materials, the warranty will be voided.

NAMEPLATE DATA

The nameplate, located on the top of the pump, indicates specific 

information about the construction of the pump. The model number 

and date code information should be recorded on the front page in the 

“Owner’s Information” section of this manual.

SHORT TERM STORAGE

When not in use, the pump should be stored and the following is advised:
•  Drain pump housing by laying pump horizontal with discharge down. 

Then stand pump on legs.

•  Store pump inside whenever possible or cover with some type of protective 

covering.

•  Tape or seal in plastic bag the terminal ends of wire leads.
•  Spray coat unpainted surfaces with rust inhibiting oil.

If panel is to be stored, the following is advised:
•  Store the panel inside whenever possible and leave in the shipping 

box.

•  All openings shall be sealed.
•  Store in an upright position.
•  Do not stack anything on top of panel.

START-UP PROCEDURE

Before placing the equipment into operation the following should be 

checked:
•  Clean pit.
•  Electrical boxes dry and securely installed.
•  Floats positioned properly.
•  Discharge valves open.
•  Adequate water level in basin for pump submersion.

Once the above has been verified proceed with the following checks:
•  Pump power cables and control floats properly installed and voltage 

verified.

•  Conduit connections to panel are properly sealed.

OPERATION

Содержание 7020

Страница 1: ...nufacturer s recommendations Table of Contents Safety Instructions 1 Limited Warranty Checklist and Application 2 3 General Information 3 Pump Wiring Instructions 4 Typical Outdoor Prepackaged System 5 Installation and Operation Instructions 6 Maintenance 7 Service Checklist 8 MAIL TO P O BOX 16347 Louisville KY 40256 0347 SHIP TO 3649 Cane Run Road Louisville KY 40211 1961 502 778 2731 1 800 928 ...

Страница 2: ...1 Grinder Pumps can be retrofitted to existing positive displacement pump installations APPLICATIONS PREINSTALLATION CHECKLIST 1 Inspectyourprogressingcavitygrinderpump Iftheunithasbeendamaged in shipment contact your dealer before installing Do Not remove the test plugs in the cover or the motor housing 2 Carefullyreadallliteraturetofamiliarizeyourselfwithdetailsregarding installation and use Ret...

Страница 3: ...ressing cavity grinder pump is an intermittent duty pump designedforpumpingsanitarysewage Itisnotadewateringortrash pump 018330ZEP 0 2 4 6 8 10 12 14 16 0 20 40 60 80 100 120 140 160 180 200 260 PUMP PERFORMANCE CURVE MODEL 7020 7021 8 16 24 32 40 48 56 64 GALLONS LITERS METERS FEET TOTAL DYNAMIC HEAD FLOW PER MINUTE 220 240 72 20 40 60 10 20 30 40 50 60 70 80 90 100 110 0 PSIG TOTAL DYNAMIC HEAD ...

Страница 4: ...6 MIN OFF Electrical Data Amps KVA Code Winding Resistance Line to Line Model BHP RPM Voltage Phase Hertz Full Load Shut Off Locked Rotor E7020 1 1750 230 1 60 7 0 7 0 24 5 G 2 3 2 0 E7021 2 1750 230 1 60 10 5 10 5 44 0 B 1 80 1 60 RE RWD7020 1 1750 230 1 60 7 0 7 0 24 5 G RE RWD7021 2 1750 230 1 60 10 5 10 5 44 0 B I7021 2 1750 200 1 60 12 12 49 5 B 1 4 1 3 RI RWH7021 2 1750 200 1 60 12 12 49 5 B...

Страница 5: ...L VALVE ALARM FLOAT PUMP CONTROL FLOAT 12 30 4 cm MIN OFF LEVEL FIBERGLASS BASIN 1 8 3 mm 302 STAINLESS STEEL LIFTING CABLE 1 1 4 FLEXIBLE DISCONNECT FITTING 1 1 4 BULK HEAD DISCHARGE FITTING 24 60 9 cm SOLID FIBERGLASS COVER GROMMET SEAL 4 INLET W SEAL FIELD INSTALLED MINIMUM 60 152 cm DISCHARGE HOSE HIGH WATER ALARM NOT INCLUDED WATERTIGHT QWIK BOX NOT INCLUDED FLOAT TREE 48 122 cm 72 183 cm 1 1...

Страница 6: ...in installation reference guide on more specific requirements 11 Note The progressing cavity grinder basin is a sewage holding tank Vent connection should be installed in accordance with all national state and local plumbing codes 12 Dig a trench for the electrical conduit Trench should be located at least 18 deep and follow all applicable NEC codes Connect electrical wiring to Junction box accord...

Страница 7: ... is located and replace disc and retainer screws Torque to 63 67 in lbs Replace cutter with the correct shims Install washerandtorquehexheadboltto71 75in lbs applyLoctite262thread lock sealant or equal to bolt threads prior to insertion Check running clearance withpumpinverticalpositiontoremoveendplay Clearancemustbebetween 0 007 and0 012 toobtainefficientgrindingwhenpumpisputbackinservice 8 Check...

Страница 8: ...long service life from the product Provided is a suggested maintenance schedule Every year Inspect basin report any sighting of grease accumulation Check for proper and unobstructed float operation Listen for proper check valve operation Every 8 years or 2 000 hours of operation Remove pump inspect and service using a Zoeller rebuild kit Flush and clean basin If the above checklist does not reveal...

Отзывы: